The ________ is a project management technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.

Correct Answer

verifed

verified

critical p...

View Answer

Which of the following statements regarding Gantt charts is true?


A) Gantt charts give a timeline and precedence relationships for each activity of a project.
B) Gantt charts use the four standard spines of Methods,Materials,Manpower,and Machinery.
C) Gantt charts are visual devices that show the duration of activities in a project.
D) Gantt charts are expensive.
E) All of the above are true.

Correct Answer

verifed

verified

Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration

Correct Answer

verifed

verified

blured image (A)Two paths are possible,ACDE and ABE....

View Answer

A network consists of the following list.Times are given in weeks. A network consists of the following list.Times are given in weeks.    a.Draw the network diagram. b.Calculate the expected duration and variance of each activity. c.Calculate the expected duration and variance of the critical path. d.Calculate the probability that the project will be completed in less than 28 weeks. a.Draw the network diagram. b.Calculate the expected duration and variance of each activity. c.Calculate the expected duration and variance of the critical path. d.Calculate the probability that the project will be completed in less than 28 weeks.

Correct Answer

verifed

verified

(a) blured image (b,c)
blured image (d)z = ...

View Answer

Which of the following statements regarding critical paths is true?


A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.

Correct Answer

verifed

verified

PERT,but not CPM,has the ability to consider the precedence relationships in a project.

Correct Answer

verifed

verified

Gantt charts give a timeline for each of a project's activities,but they do not adequately illustrate the interrelationships between the activities and the resources.

Correct Answer

verifed

verified

WBS stands for which of the following project management tools?


A) work break schedule
B) work breakdown status
C) work breakdown schedule
D) work breakdown structure
E) work break status

Correct Answer

verifed

verified

Given the critical path below,calculate the following: a.The crash cost per unit time savings for each activity. b.The maximum total crash time savings and cost. c.The maximum total time-savings with a $3000 budget. Given the critical path below,calculate the following: a.The crash cost per unit time savings for each activity. b.The maximum total crash time savings and cost. c.The maximum total time-savings with a $3000 budget.

Correct Answer

verifed

verified

(A)A saves 1 day for $4000/day,B saves 2...

View Answer

Which of these statements regarding time-cost tradeoffs in CPM networks is true?


A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration,but noncritical,activities.
C) Activities not on the critical path can never be on the critical path,even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) The crash time always exceeds the normal time.

Correct Answer

verifed

verified

In PERT analysis,the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

Correct Answer

verifed

verified

Identify,in order,the six steps basic to both PERT and CPM.

Correct Answer

verifed

verified

1.Define the project and prepare the WBS...

View Answer

A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.


A) The critical path is D-E-F,duration 15.
B) The critical path is D-F,duration 12.
C) Slack at D is 3 periods.
D) Slack at E is 3 periods.
E) Both A and C are true.

Correct Answer

verifed

verified

The control of projects involves close monitoring of which of the following?


A) resources
B) costs
C) quality
D) budgets
E) all of the above

Correct Answer

verifed

verified

A project being analyzed by PERT has 60 activities,13 of which are on the critical path.If the estimated time along the critical path is 214 days with a project variance of 100,what is the probability that the project will take 224 days or more to complete?


A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14

Correct Answer

verifed

verified

The network below represents a project being analyzed by the critical path method.Activity durations are indicated on the network. The network below represents a project being analyzed by the critical path method.Activity durations are indicated on the network.   a.Identify the activities on the critical path. b.What is the duration of the critical path? c.Calculate the amount of slack time at activity H. d.If activity I were delayed by ten time units,what would be the impact on the project duration? a.Identify the activities on the critical path. b.What is the duration of the critical path? c.Calculate the amount of slack time at activity H. d.If activity I were delayed by ten time units,what would be the impact on the project duration?

Correct Answer

verifed

verified

(a)Critical activities are A-C...

View Answer

A project organization that becomes permanent is often referred to as a:


A) fixed project organization.
B) matrix organization.
C) normal organization.
D) standard organization.
E) permanent project organization.

Correct Answer

verifed

verified

What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept.11,2001?


A) Project Panther
B) Project Pit Bull
C) Project Python
D) Project Piranha
E) Project Phoenix

Correct Answer

verifed

verified

The network analysis method that allows activity times to vary is ________.

Correct Answer

verifed

verified

PERT or Pr...

View Answer

One responsibility of a project manager is to make sure that the project meets its quality goals.

Correct Answer

verifed

verified