A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
Correct Answer
verified
Multiple Choice
A) 3
B) 6
C) 9
D) 18
E) None of the above
Correct Answer
verified
Multiple Choice
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 2.33
B) 5.44
C) 8.00
D) 64.00
E) None of the above
Correct Answer
verified
Multiple Choice
A) 0
B) 5
C) 3
D) 6
E) None of the above
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above
Correct Answer
verified
Multiple Choice
A) B
B) D
C) E
D) C
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 5.222
B) 4.364
C) 1.362
D) 5.144
E) 2.362
Correct Answer
verified
Multiple Choice
A) path with the least variance.
B) path with zero slack.
C) path with the most activities.
D) path with the largest variance.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 108.0
B) 160.4
C) 166.5
D) 135.0
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the times to complete individual activities are known with certainty.
B) all activities are carried out by staff from our own organization.
C) the total cost of a project is independent of the time to complete the project.
D) the total time to complete all activities on the critical path is described by a normal distribution.
E) None of the above
Correct Answer
verified
Multiple Choice
A) When will the entire project be completed?
B) What is the probability that the project will be completed by a specific date?
C) What are the critical activities?
D) What are the noncritical activities?
E) All of the above
Correct Answer
verified
Multiple Choice
A) the normal time to complete an activity.
B) the most pessimistic time to complete an activity.
C) the incremental decrease in the time to complete an activity.
D) the shortened activity time.
E) None of the above
Correct Answer
verified
Multiple Choice
A) 8
B) 12
C) 18
D) 10
E) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer