A) drawing the activities in a ladder arrangement.
B) drawing the activities in a loop format.
C) drawing the activities in a serial relationship.
D) drawing all the activities with a common start date.
Correct Answer
verified
Multiple Choice
A) based on each activity's earliest start time.
B) based on each activity's earliest finish time.
C) based on each activity's latest start time.
D) based on each activity's latest finish time.
Correct Answer
verified
Multiple Choice
A) Resource evaluation scheduling
B) Resource monitoring
C) Resource limited scheduling
D) Resource leveling
Correct Answer
verified
Multiple Choice
A) the priorities of the activities to display in the resource requirements plan.
B) the types and quantities of resources required to perform each activity.
C) the dependent relationship between resources and show the relationships in the network diagram.
D) only the non-critical activities and their resources.
Correct Answer
verified
Multiple Choice
A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
Correct Answer
verified
Multiple Choice
A) 56 days
B) 28 days
C) 14 days
D) Additional information is needed to determine the project duration.
Correct Answer
verified
Multiple Choice
A) Project management information systems
B) Formulas and techniques
C) Trial and error techniques
D) Calendaring systems
Correct Answer
verified
Multiple Choice
A) resource limited scheduling
B) resource monitoring
C) resource leveling
D) resource evaluation scheduling
Correct Answer
verified
Multiple Choice
A) when each is taking vacation time or time off.
B) know the name of each resource on the project.
C) list all the projects to which the resources have been assigned.
D) indicate the amounts and types of resources needed to perform each activity.
Correct Answer
verified
Multiple Choice
A) who is responsible for which activities.
B) the amount of labor expenses for the project.
C) the expected utilization of resources by time period during the time span of the project.
D) the budget for material and cost resources.
Correct Answer
verified
Multiple Choice
A) as-soon-as-possible
B) as-late-as-possible
C) as-needed
D) as-flexible-as-possible
Correct Answer
verified
Multiple Choice
A) drawing the activities with common resources in a loop format.
B) drawing the activities to reflect the availability of a limited quantity of resources.
C) drawing the activities with different resources in a serial relationship.
D) drawing the activities with a common finish date.
Correct Answer
verified
Multiple Choice
A) each of the activities are independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Correct Answer
verified
Multiple Choice
A) Three workers per day
B) 21 worker-days
C) Seven days
D) Additional information is needed to determine the minimum number.
Correct Answer
verified
Multiple Choice
A) Test resolutions to any scheduling conflicts.
B) Use the nine-step problem solving method in the system.
C) Level or smooth the resources automatically.
D) Create charges for resources.
Correct Answer
verified
Multiple Choice
A) the maximum number of project resources should be hired for the project duration.
B) if the workers are employed for the duration of the project and it may be necessary to pay them when idle or overtime when at peak demand.
C) the actual work performed for each activity should be evaluated to inform the next activity of the number of workers needed.
D) all projects should plan all tasks for one person to complete the activities to keep the person busy.
Correct Answer
verified
Multiple Choice
A) The critical path of the project had negative slack.
B) Tasks using the same resources that were leveled were not on the critical path.
C) At least one of the activities using the resources that were leveled had positive slack.
D) The project had adequate positive slack in all the paths to accommodate the leveling.
Correct Answer
verified
Multiple Choice
A) all activities with a positive slack
B) all non-critical activities
C) all critical activities
D) only non-critical activities with positive slack
Correct Answer
verified
Multiple Choice
A) without extending the project beyond its required completion time.
B) by assigning one resource to work per day.
C) by extending the project beyond its required completion time.
D) by adding additional resources to the project.
Correct Answer
verified
Multiple Choice
A) referential
B) technical
C) check
D) entity
Correct Answer
verified