Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.


A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.

Correct Answer

verifed

verified

If three activities are using the same resource, the network diagram must be draw


A) to show the three activities so that none is a predecessor of the others.
B) to show the three activities performed at the same time.
C) to show the activity sequence with technical constraints only
D) to show a serial relationship for the activities.

Correct Answer

verifed

verified

Resource leveling, or smoothing, is a method for


A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.

Correct Answer

verifed

verified

The resource requirements plan illustrates


A) the utilization of human resources and their primary responsibility.
B) how the resources should be leveled.
C) the expected utilization of resources by time period during the time span of the project.
D) the primary and secondary responsibilities for the project.

Correct Answer

verifed

verified

Why are activities drawn in a serial relationship in a network diagram?


A) The activities use different resources.
B) The activities are independent of each other.
C) From a technical standpoint, the activities must be performed in that sequence.
D) The order of completion doesn't matter.

Correct Answer

verifed

verified

Resource utilization charts based on each activity's earliest start time are said to be based on an ____ schedule.


A) as-soon-as-possible
B) as-late-as-possible
C) as-needed
D) as-flexible-as-possible

Correct Answer

verifed

verified

When several activities need the same limited resource at the same time, the activities with


A) the least slack have first priority.
B) the longest duration have first priority.
C) the near term have first priority.
D) use the most resources have first priority.

Correct Answer

verifed

verified

In resource-limited scheduling, the lower priority activities get delayed.How does the delaying of activities affect the project?


A) The delaying of activities increases the costs of the project.
B) The delaying of activities decreases the acceptance of the project deliverable.
C) The delaying of activities may delay the project.
D) The delaying of activities helps give others more time on their tasks because they won't affect the project schedule.

Correct Answer

verifed

verified

This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number. This example has level resources of three resources for eight days.If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.   A)  Paths would be 1,2,3,5 and 1,2,4 B)  Paths would be 1,2,3,4 and 1,2,5 C)  Paths would be 1,2 and 3,4,5 D)  Path would be 1,2,3,4,5


A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5

Correct Answer

verifed

verified

Activities in a network diagram are drawn in a ____ relationship because, from a technical standpoint, they must be performed in that sequence.


A) parallel
B) vector
C) serial
D) interlocking

Correct Answer

verifed

verified

Which of following would allow for level resources on the project?


A)
Which of following would allow for level resources on the project? A)    B)    C)    D)
B)
Which of following would allow for level resources on the project? A)    B)    C)    D)
C)
Which of following would allow for level resources on the project? A)    B)    C)    D)
D)
Which of following would allow for level resources on the project? A)    B)    C)    D)

Correct Answer

verifed

verified

Resource utilization charts based on each activity's latest start time are said to be based


A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.

Correct Answer

verifed

verified

In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?


A) Activities that use the same resource may not be able to occur in parallel to each other.
B) Activities that use different resources may be shown in a serial relationship.
C) The activities could be shown in a loop relationship.
D) Resources that are unlimited are not shown in a resource assignment.

Correct Answer

verifed

verified

The start of noncritical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to


A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.

Correct Answer

verifed

verified

Resource leveling, or smoothing, levels the resources so that


A) equal number of resources is assigned to each task.
B) an equal number of tasks are completed each day by the resources on the project.
C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
D) the costs for the resources are even as possible across the project.

Correct Answer

verifed

verified

Resources in a project are


A) human resources only
B) work, material, or cost resources
C) always assigned in a resource-limited manner
D) unlimited in quantity

Correct Answer

verifed

verified

If not enough resources are available for a project, to maintain the same project scope and budget, the project team should


A) accelerate the activities that have enough resources to free the needed resources.
B) delay some activities until the resource is available.
C) hire additional resources.
D) start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work.

Correct Answer

verifed

verified

____ is an iterative method in which resources are allocated to activities based on the least slack.


A) Resource evaluation scheduling
B) Resource monitoring
C) Resource leveling
D) Resource limited scheduling

Correct Answer

verifed

verified

Resource-limited scheduling will not extend the project completion time if necessary in order to keep within the resource limits.

Correct Answer

verifed

verified

Resource-limited scheduling attempts a schedule in which the number of resources is limited and


A) the schedule may be extended to keep the resource limits.
B) the schedule is shortened because the limit for resources is raised.
C) the shortest schedule is developed by reducing the project scope.
D) priorities are given to the activities to limit the time for each activity.

Correct Answer

verifed

verified

Showing 21 - 40 of 45