Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) outlines the major tasks or work elements to be performed.
B) lists the specifications and attributes of the customer's requirements.
C) states the acceptance criteria for the project's deliverables.
D) indicates the due date of the proposal.
Correct Answer
verified
Multiple Choice
A) the requirements for the number of contractors to bid on the project.
B) the acceptance criteria for the project.
C) the specifications and attributes of the proposed solution.
D) the major tasks to be completed in the project.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) clarify the RFP and answer any questions from potential bidders.
B) provide additional information only to those that attend the meeting.
C) provide an unfair advantage to those at the meeting.
D) solicit feedback on the clarity of the RFP to change the project requirements.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Needs resolution
B) Needs identification
C) Problem generation
D) Brainstorming
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the project objective.
B) the detailed description of the project.
C) the key conditions and parameters of the project.
D) the funding and contracting of the project.
Correct Answer
verified
Multiple Choice
A) an intangible benefit.
B) a return on investment.
C) a tangible benefit.
D) a project task.
Correct Answer
verified
Multiple Choice
A) summarize the need and justification for the project.
B) state what is expected to be accomplished.
C) state the major end products or items expected to be produced.
D) be concise and create a vision for the end result of the project.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) the tangible items that the contractor is to provide.
B) the key milestones to meet.
C) products such as an increase in employee morale or improved company image.
D) key elements of the evaluation criteria for deciding what project to select.
Correct Answer
verified
Multiple Choice
A) keep the RFP a secret until the time for soliciting for bids.
B) only distribute the RFP in newspapers and websites.
C) identify select contractors that would bid on the project and share the RFP with them.
D) provide select information to a few companies rather than all that might be interested in submitting a proposal.
Correct Answer
verified
Showing 41 - 60 of 92