A) 14.36%
B) 10.17%
C) 17.42%
D) 12.70%
E) 21.53%
Correct Answer
verified
Multiple Choice
A) 2 years
B) 4 years
C) 6 years
D) 8 years
E) 10 years
Correct Answer
verified
Multiple Choice
A) 12.0%
B) 11.5%
C) 12.3%
D) 14.1%
E) 13.0%
Correct Answer
verified
Multiple Choice
A) -$10,640
B) $19,879
C) $20,485
D) $19,380
E) -$19,879
Correct Answer
verified
Multiple Choice
A) Equal to the IRR
B) Too high
C) Greater than the IRR
D) Too low
E) Less than the IRR
Correct Answer
verified
Multiple Choice
A) Project A
B) Project B
C) Either Project A or Project B
D) Both Projects
Correct Answer
verified
Multiple Choice
A) 14.24%
B) 15.24%
C) 15.74%
D) 16.24%
E) 16.74%
Correct Answer
verified
Multiple Choice
A) internal rate of return is less than the cost of capital
B) internal rate of return exceeds the cost of capital
C) cost of capital exceeds the internal rate of return
D) internal rate of return exceeds the firm's cost of debt
E) internal rate of return exceeds the firm's cost of equity
Correct Answer
verified
Multiple Choice
A) The NPV will be positive if the IRR is less than the cost of capital.
B) If the multiple IRR problem does not exist, any independent project acceptable by NPV method will also be acceptable by the IRR method.
C) When IRR = k (the cost of capital) , NPV = 0.
D) The IRR can be positive even if the NPV is negative.
E) The NPV method is not affected by the multiple IRR problem.
Correct Answer
verified
Multiple Choice
A) does not employ time value of money techniques.
B) is easy to use when available capital or resources are limited.
C) does not rely on the cost of capital.
D) provides its users with a clear decision criterion.
E) provides a "bang for the buck" analysis for each project.
Correct Answer
verified
Multiple Choice
A) $3,500,000
B) $3,267,754
C) $5,243,412
D) $13,267,75
E) $82,874,276
Correct Answer
verified
Multiple Choice
A) 2 months
B) 2.02 years
C) 3.4 years
D) 7 years
E) 24 years
Correct Answer
verified
Multiple Choice
A) Larger than $70; hard to tell without more information
B) Much less than $70, as the project clearly had a large, negative NPV
C) About $70; the NPV of the project was close to zero
D) $70; the NPV of a project does not affect the stock price
Correct Answer
verified
Multiple Choice
A) ignores the time value of money.
B) has no clearly defined decision rule.
C) does not consider cash flows that occur beyond the payback period.
D) does not adjust for risk.
E) does not provide a good measure of the project's liquidity.
Correct Answer
verified
Multiple Choice
A) accept both if their cost of capital is 15% at the maximum.
B) accept only Z if their cost of capital is 15% at the maximum.
C) accept only X if their cost of capital is 15% at the maximum.
D) reject both if their cost of capital is 12% at the maximum.
Correct Answer
verified
Multiple Choice
A) 0.935
B) 0.981
C) 0.995
D) 1.333
E) 1.981
Correct Answer
verified
Multiple Choice
A) 8%
B) 14%
C) 18%
D) -5%
E) 12%
Correct Answer
verified
Multiple Choice
A) $15,819.27
B) $21,937.26
C) $32,415.85
D) $38,000.00
E) $52,815.71
Correct Answer
verified
Multiple Choice
A) the sum of all cash inflows and outflows is positive.
B) the difference between all discounted cash inflows and outflows exceeds zero.
C) it lowers costs below an acceptable hurdle rate.
D) its rate of return is greater than the firm's cost of capital.
E) it returns the initial investment faster than competing projects.
Correct Answer
verified
Multiple Choice
A) 3 years
B) 4 years
C) 5 years
D) The project is not paid off in this time frame.
E) Need the cost of capital to answer this question.
Correct Answer
verified
Showing 41 - 60 of 86
Related Exams