The length of time expected to complete an activity assuming that its development proceeds normally is called the:


A) Optimistic duration.
B) Pessimistic duration.
C) Most likely duration.
D) Normal duration.

Correct Answer

verifed

verified

  -Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity? A)  6, 20 B)  6, 26 C)  9, 20 D)  9, 26 -Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity?


A) 6, 20
B) 6, 26
C) 9, 20
D) 9, 26

Correct Answer

verifed

verified

Discuss any five approaches to reducing the critical path. Which is the most effective and which is the most difficult to achieve? Why?

Correct Answer

verifed

verified

The text presents eight ways to reduce t...

View Answer

Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.

Correct Answer

verifed

verified

Hammock activities allow:


A) Project managers to streamline the linkage and sequencing between activities.
B) Project workers to effectively skip nonessential activities without compromising project quality.
C) The project team to better disaggregate the overall project network into subsets.
D) The project manager to identify float more quickly and leverage it more successfully for the overall success of the project.

Correct Answer

verifed

verified

Negative float exists when a project's critical path has been completed more quickly than anticipated.

Correct Answer

verifed

verified

Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other path be watched and why? Use the values in the table to calculate activity durations and variances for the project. Which path is critical? How closely should the other path be watched and why?

Correct Answer

verifed

verified

The critical path is ACEF at 34.17 days ...

View Answer

These can be located by doing a backward pass through a network.


A) Critical paths
B) Merge activities
C) Successors
D) Burst activities

Correct Answer

verifed

verified

Use the values in the table to calculate activity durations and variances for the project. What is the likelihood of finishing this project within 47 days? Use the values in the table to calculate activity durations and variances for the project. What is the likelihood of finishing this project within 47 days?

Correct Answer

verifed

verified

The estimated activity lengths and varia...

View Answer

What is the early start time for Activity G given the activity times and precedence requirements shown in the table? What is the early start time for Activity G given the activity times and precedence requirements shown in the table?   A)  22 B)  21 C)  20 D)  19


A) 22
B) 21
C) 20
D) 19

Correct Answer

verifed

verified

  -What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days? A)  Day 15 B)  Day 7 C)  Day 5 D)  Day 3 -What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days?


A) Day 15
B) Day 7
C) Day 5
D) Day 3

Correct Answer

verifed

verified

Phoebe B. Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project. She calculated early and late start times and early and late finish times but spilled coffee all over her printout. Use the remaining information to reconstruct the table for Phoebe B. Beebee and her new canoe canal. Phoebe B. Beebee is constructing a canal for the annual canoe races and has identified eleven activities that are required to complete this important project. She calculated early and late start times and early and late finish times but spilled coffee all over her printout. Use the remaining information to reconstruct the table for Phoebe B. Beebee and her new canoe canal.

Correct Answer

verifed

verified

The comple...

View Answer

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity. What are the early start and late finish times associated with this hammock activity?   A)  13, 36 B)  13, 24 C)  24, 36 D)  7, 36


A) 13, 36
B) 13, 24
C) 24, 36
D) 7, 36

Correct Answer

verifed

verified

You must know the mean of an activity in order to determine its standard deviation.

Correct Answer

verifed

verified

What is the early start time for Activity D given the activity times and precedence requirements shown in the table? What is the early start time for Activity D given the activity times and precedence requirements shown in the table?   A)  7 B)  9 C)  11 D)  13


A) 7
B) 9
C) 11
D) 13

Correct Answer

verifed

verified

Summaries for some subsets of the activities identified in the overall project network are called:


A) Ladder activities.
B) Hammock activities.
C) Negative float activities.
D) Compressed activities.

Correct Answer

verifed

verified

An activity has an optimistic time estimate of 17 days, a most likely estimate of 23 days, and a pessimistic estimate of 37 days. What is the variance of the activity?


A) 3.33
B) 6.66
C) 9.99
D) 11.11

Correct Answer

verifed

verified

One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n) :


A) Event.
B) Path.
C) Node.
D) Burst.

Correct Answer

verifed

verified

  -Network logic suggests that: A)  Activity D can start any time. B)  Activity A must be complete before Activity B can be done. C)  Activities A, B and C must be complete before Activity D can be done. D)  Activity C must begin before Activity B begins. -Network logic suggests that:


A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.

Correct Answer

verifed

verified

Prior to creating a network, it is important to:


A) Identify all loops through activities.
B) Identify the party responsible for each activity.
C) Calculate the float for each activity.
D) Understand the activity precedence.

Correct Answer

verifed

verified