Correct Answer
verified
Multiple Choice
A) 0 units
B) 10 units
C) 20 units
D) 40 units
Correct Answer
verified
Multiple Choice
A) setup time.
B) materials handling and waiting times.
C) process time.
D) all the above
Correct Answer
verified
Multiple Choice
A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 2 is 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 4 are at least 65 units.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) It provides more extensive information than MRP because it is tied to the company's financial system.
B) It incorporates informal systems through the use of expert systems technology.
C) It is computationally faster than regular MRP.
D) It is limited only to aiding order- launching decisions.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) secret document to prompt actions to be taken against some suppliers.
B) computer- generated document that helps make decisions about releasing new orders.
C) document that records the most recent important actions taken in the context of MRP.
D) legal notice served by a customer whose order was delayed.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) POQ, P = 3
B) FOQ = 75
C) FOQ = 100
D) L4L
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) The scheduled receipts for a parent item are used to calculate the gross requirements for components of that parent.
B) Some of the key inputs to a computerized MRP system are inventory records, updated bills of material, and a valid master production schedule.
C) One of the main prerequisites for implementing an MRP system is to have products with few BOM levels.
D) Benefits of a successful MRP implementation typically include a decrease in the number of inventory turns, and an increase in the number of expediters.
Correct Answer
verified
Showing 121 - 140 of 174