A) 9.70%
B) 10.78%
C) 11.98%
D) 13.31%
E) 14.64%
Correct Answer
verified
Multiple Choice
A) Since the smaller project has the higher IRR, the two projects' NPV profiles cannot cross, and the smaller project's NPV will be higher at all positive values of WACC.
B) Since the smaller project has the higher IRR, the two projects' NPV profiles will cross, and the larger project will look better based on the NPV at all positive values of WACC.
C) If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger, longer-term projects, regardless of how high or low the WACC is.
D) Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount rate, the two projects' NPV profiles will cross, and the larger project will have the higher NPV if the WACC is less than the crossover rate.
E) Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects' NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover rate.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $134.79
B) $141.89
C) $149.36
D) $164.29
E) $205.36
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 13.13%
B) 14.44%
C) 15.89%
D) 17.48%
E) 19.22%
Correct Answer
verified
Multiple Choice
A) A project's IRR increases as the WACC declines.
B) A project's NPV increases as the WACC declines.
C) A project's MIRR is unaffected by changes in the WACC.
D) A project's regular payback increases as the WACC declines.
E) A project's discounted payback increases as the WACC declines.
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
E) If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive.
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
Multiple Choice
A) The MIRR and NPV decision criteria can never conflict.
B) The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
C) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
D) The higher the WACC, the shorter the discounted payback period.
E) The MIRR method assumes that cash flows are reinvested at the crossover rate.
Correct Answer
verified
Multiple Choice
A) $105.89
B) $111.47
C) $117.33
D) $123.51
E) $130.01
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV) , then discounting the TV at the WACC.
B) A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV) , then discounting the TV to find the IRR.
C) If a project's IRR is smaller than the WACC, then its NPV will be positive.
D) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost.
E) If a project's IRR is positive, then its NPV must also be positive.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
B) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
C) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
D) If a project's NPV is greater than zero, then its IRR must be less than zero.
E) The NPVs of relatively risky projects should be found using relatively low WACCs.
Correct Answer
verified
Showing 61 - 80 of 107
Related Exams