A) should not be prepared in a company.
B) is useful in evaluating a manager's performance by comparing actual variable costs and planned variable costs.
C) shows planned results at the original budgeted activity level.
D) is changed only if the actual level of activity is different than originally budgeted.
Correct Answer
verified
Multiple Choice
A) daily.
B) monthly.
C) weekly.
D) as frequently as needed.
Correct Answer
verified
Multiple Choice
A) 160,000 hours and 165,000 hours.
B) 165,000 hours and 150,000 hours.
C) 160,000 hours and 150,000 hours.
D) 150,000 hours and 150,000 hours.
Correct Answer
verified
Multiple Choice
A) 4%
B) 35%
C) 6%
D) 1.5%
Correct Answer
verified
Multiple Choice
A) Investment and profit centers
B) Profit and cost centers
C) Cost and investment centers
D) Only profit centers
Correct Answer
verified
Multiple Choice
A) fewer costs are controllable.
B) the responsibility for cost incurrence diminishes.
C) a greater number of costs are controllable.
D) performance evaluation becomes less important.
Correct Answer
verified
Multiple Choice
A) total costs with static budget data.
B) total costs with flexible budget data.
C) controllable costs with static budget data.
D) controllable costs with flexible budget data.
Correct Answer
verified
Multiple Choice
A) common fixed costs.
B) direct fixed costs.
C) indirect fixed costs.
D) noncontrollable fixed costs.
Correct Answer
verified
Multiple Choice
A) substantial fixed costs.
B) substantial variable costs.
C) planned activity levels that match actual activity levels.
D) no variable costs.
Correct Answer
verified
Multiple Choice
A) 96,000 hours and 99,000 hours.
B) 99,000 hours and 90,000 hours.
C) 96,000 hours and 90,000 hours.
D) 90,000 hours and 90,000 hours.
Correct Answer
verified
Multiple Choice
A) linear and upward sloping.
B) linear and downward sloping.
C) curvilinear and upward sloping.
D) linear to a point and then level off.
Correct Answer
verified
Multiple Choice
A) Both projects
B) Project A
C) Project B
D) Neither project
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $144,000.
B) $162,000.
C) $157,500.
D) $148,500.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $4,000 unfavorable
B) $4,000 favorable
C) $12,000 unfavorable
D) $16,000 favorable
Correct Answer
verified
Multiple Choice
A) activity index and the relevant range of activity.
B) variable costs and determine the budgeted variable cost per unit.
C) fixed costs and determine the budgeted fixed cost per unit.
D) All of these options are steps in developing the flexible budget.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Another name for a flexible budget
B) The degree to which the CFO controls the budget
C) The use of budgets in controlling operations
D) The process of providing information on budget differences to lower level managers
Correct Answer
verified
Multiple Choice
A) control selling expenses.
B) determine whether income objectives are being met.
C) determine whether sales goals are being met.
D) control sales commissions.
Correct Answer
verified
Showing 41 - 60 of 159
Related Exams