Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) drawing the project AON network
B) identifying the critical path
C) drawing the project AOA network
D) tracking the progress of the project
E) creating the project Gantt chart
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) Level 1, Level 2, Level 4, Level 3, Level 3
B) Level 1, Level 2, Level 3, Level 4, Level 5
C) Level 0, Level 1, Level 2, Level 3, Level 4
D) Level 0, Level 2, Level 2, Level 3, Level 3
E) Level 5, Level 3, Level 4, Level 1, Level 2
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) AOA networks sometimes require dummy activities.
B) nodes consume no resources or time in AOA networks.
C) both are acceptable in practice; however, Microsoft Project uses AON.
D) nodes designate activities in AON, while arrows designate activities in AOA.
E) All of the these are true.
Correct Answer
verified
Multiple Choice
A) Hoover Dam
B) Boston Central Artery/Tunnel
C) Trans-Arabian Pipeline
D) Channel Tunnel
E) Getty Center
Correct Answer
verified
Multiple Choice
A) 98
B) 112
C) 120
D) 124
E) 220
Correct Answer
verified
Multiple Choice
A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) none of these.
Correct Answer
verified
Multiple Choice
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) 5.00
B) 5.50
C) 6.00
D) 3.00
E) 33.00
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14
Correct Answer
verified
Multiple Choice
A) the simple average of the optimistic, pessimistic, and most likely times.
B) the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b.
C) the sum of the optimistic, pessimistic, and most likely times.
D) the sum of the optimistic, pessimistic, and most likely times, divided by six.
E) the sum of the activity variances, divided by six.
Correct Answer
verified
Showing 41 - 60 of 131