Ethical issues that can arise in projects include gifts from contractors, pressure to mask delays with false status reports, false reports for charges of time and expenses, and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.

Correct Answer

verifed

verified

Describe in words how to calculate a project's standard deviation. What assumption allows that calculation to be accurate?

Correct Answer

verifed

verified

Add the variances of the activ...

View Answer

Which of the following is NOT performed by Microsoft Project?


A) drawing the project AON network
B) identifying the critical path
C) drawing the project AOA network
D) tracking the progress of the project
E) creating the project Gantt chart

Correct Answer

verifed

verified

Define slack time.

Correct Answer

verifed

verified

Slack time is the le...

View Answer

The shortest of all paths through the network is the critical path.

Correct Answer

verifed

verified

Match the following steps in Microsoft's development of Windows 10 to their respective WBS level. Step Level Develop Windows 10 Operating System ? System Testing ? Compatible with Windows 8 ? Develop GUI's ? Module Testing ?


A) Level 1, Level 2, Level 4, Level 3, Level 3
B) Level 1, Level 2, Level 3, Level 4, Level 5
C) Level 0, Level 1, Level 2, Level 3, Level 4
D) Level 0, Level 2, Level 2, Level 3, Level 3
E) Level 5, Level 3, Level 4, Level 1, Level 2

Correct Answer

verifed

verified

The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network. The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.    (a) Identify the activities on the critical path. (b) What is the duration of the critical path? (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time units, what would be the impact on the project duration? (a) Identify the activities on the critical path. (b) What is the duration of the critical path? (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time units, what would be the impact on the project duration?

Correct Answer

verifed

verified

(a) Critical activities are A-...

View Answer

One phase of a large project is scheduling.

Correct Answer

verifed

verified

The difference between AON and AOA networks is that:


A) AOA networks sometimes require dummy activities.
B) nodes consume no resources or time in AOA networks.
C) both are acceptable in practice; however, Microsoft Project uses AON.
D) nodes designate activities in AON, while arrows designate activities in AOA.
E) All of the these are true.

Correct Answer

verifed

verified

Which of the following projects was NOT completed by Bechtel?


A) Hoover Dam
B) Boston Central Artery/Tunnel
C) Trans-Arabian Pipeline
D) Channel Tunnel
E) Getty Center

Correct Answer

verifed

verified

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day) ?


A) 98
B) 112
C) 120
D) 124
E) 220

Correct Answer

verifed

verified

The beta distribution is used in project management to:


A) determine which activity should be crashed.
B) calculate the probability that a project will be completed within its budget.
C) calculate expected activity times.
D) calculate slack for activities on the critical path.
E) none of these.

Correct Answer

verifed

verified

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 22. Which of the following is definitely TRUE?


A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.

Correct Answer

verifed

verified

The ________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.

Correct Answer

verifed

verified

An activity on a PERT network has these time estimates: optimistic = 3, most likely = 5, and pessimistic = 10. What is its expected activity time?


A) 5.00
B) 5.50
C) 6.00
D) 3.00
E) 33.00

Correct Answer

verifed

verified

Slack is the amount of time an activity can be delayed without delaying the entire project.

Correct Answer

verifed

verified

Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.

Correct Answer

verifed

verified

PERT, but not CPM, has the ability to consider the precedence relationships in a project.

Correct Answer

verifed

verified

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take less than 224 days to complete?


A) near zero
B) 0.0126
C) 0.1587
D) 0.8413
E) 2.14

Correct Answer

verifed

verified

The expected activity time in PERT analysis is calculated as:


A) the simple average of the optimistic, pessimistic, and most likely times.
B) the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b.
C) the sum of the optimistic, pessimistic, and most likely times.
D) the sum of the optimistic, pessimistic, and most likely times, divided by six.
E) the sum of the activity variances, divided by six.

Correct Answer

verifed

verified

Showing 41 - 60 of 131