Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) .


A) Monday, May 18, 2020
B) Tuesday, May 19, 2020
C) Friday, May 22, 2020
D) Tuesday, May 26, 2020
E) Monday, May 25, 2020

Correct Answer

verifed

verified

List and briefly describe the disadvantages of resource leveling or smoothing.

Correct Answer

verifed

verified

More criti...

View Answer

In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project.


A) equipment
B) time
C) technical
D) resource
E) logical

Correct Answer

verifed

verified

A lack of readily available engineers is a technical constraint.

Correct Answer

verifed

verified

Too many parallel activities for one individual is an example of a resource constraint.

Correct Answer

verifed

verified

A shortage of software developers to create software is an example of a(n) ________ type of resource constraint.


A) physical
B) people
C) material
D) equipment
E) budget

Correct Answer

verifed

verified

To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.

Correct Answer

verifed

verified

Which of the following questions does a project manager NOT have to address when considering resources allocated to a project?


A) Will the assigned labor be adequate and available to deal with my project?
B) Will outside contractors have to be used?
C) Will scope have to be redefined / stabilized?
D) Do unforeseen resource dependencies exist?
E) How much flexibility do we have in using resources?

Correct Answer

verifed

verified

A project cost baseline is also called __________.


A) earned value (EV)
B) actual cost (AC)
C) planned value (PV)
D) budget distribution
E) budget allocation

Correct Answer

verifed

verified

In a resource-constrained project, which of the following is most likely to be changed?


A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep

Correct Answer

verifed

verified

When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:


A) Over Allocated.
B) Time-Constrained.
C) Institutionally Challenged.
D) Ahead of schedule.
E) Unstable.

Correct Answer

verifed

verified

Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.

Correct Answer

verifed

verified

In a resource-constrained project, the completion date is most likely to change.

Correct Answer

verifed

verified

Why is it necessary to have a time-phased budget baseline?


A) It allows proper resource allocation.
B) It shows how much work was accomplished for the money spent.
C) It reduces schedule slippage when scheduling multiproject resources.
D) It is not necessary to have a time-phased budget baseline.
E) It reduces fluctuations in cash flow during the project.

Correct Answer

verifed

verified

Project management software is important because it will manage the project for the project manager.

Correct Answer

verifed

verified

Why is a schedule not a schedule until resources have been assigned? Provide a real-life example that illustrates your explanation.

Correct Answer

verifed

verified

Before resources are assigned it is assu...

View Answer

Without a time-phased budget a good project schedule and cost control are impossible.

Correct Answer

verifed

verified

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) . All activities require the same resource. Assume no working-day holidays during the months of May and June-no Memorial Day holiday, for example.


A) Monday, June 8, 2020
B) Wednesday, June 10, 2020
C) Friday, June 5, 2020
D) Thursday, June 11, 2020
E) Thursday, June 4, 2020

Correct Answer

verifed

verified

In a resource-constrained project, the first, or primary, priority in assigning resources is usually given to activities with the


A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.

Correct Answer

verifed

verified

When using the _______ scheduling technique, startup and shutdown costs are major considerations.


A) splitting
B) critical path method
C) PERT
D) laddering
E) lags

Correct Answer

verifed

verified