Filters
Question type

An amusement park estimates average costs per day. Which of the following is true?


A) Average cost per day considers the relationship between labor costs and other variables such as temperature
B) Average cost per day can be useful in estimating labor costs
C) Average cost per day would include a component of variable labor costs but not fixed labor cost
D) All of the above

Correct Answer

verifed

verified

Use the following to answer questions: (CMA adapted) The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows: Use the following to answer questions: (CMA adapted)  The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows:     t-table for Single-Tailed Values of t    -The percent of the change in the maintenance costs that can be explained by a change in the activity hours is: A)  68.46% B)  12.12% C)  34.47% D)  99.72% t-table for Single-Tailed Values of t Use the following to answer questions: (CMA adapted)  The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows:     t-table for Single-Tailed Values of t    -The percent of the change in the maintenance costs that can be explained by a change in the activity hours is: A)  68.46% B)  12.12% C)  34.47% D)  99.72% -The percent of the change in the maintenance costs that can be explained by a change in the activity hours is:


A) 68.46%
B) 12.12%
C) 34.47%
D) 99.72%

Correct Answer

verifed

verified

The correlation coefficient that indicates the strongest linear association between two variables is:


A) -0.92
B) -0.74
C) 0.45
D) 0.74

Correct Answer

verifed

verified

A particular manufacturing job is subject to an estimated 90% learning curve. The first unit required 40 labor hours to complete. What is the cumulative average time per unit after four units are completed?


A) 32.0 hours
B) 32.4 hours
C) 36.0 hours
D) 40.0 hours

Correct Answer

verifed

verified

A regression equation:


A) Estimates the independent variable
B) Is based on objective and constraint functions
C) Encompasses factors outside the relevant range
D) Estimates the dependent variable

Correct Answer

verifed

verified

Multiple regression is a regression equation with more than one independent variable.

Correct Answer

verifed

verified

Use the following to answer questions: (CMA adapted) The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows: Use the following to answer questions: (CMA adapted)  The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows:     t-table for Single-Tailed Values of t    -Based upon the information from the regression analysis, the total maintenance costs budgeted for 420 hours of activity would be (rounded to the nearest whole dollar) : A)  $3,746 B)  $3,780 C)  $3,797 D)  $3,461 t-table for Single-Tailed Values of t Use the following to answer questions: (CMA adapted)  The following information has been accumulated to be used in preparing the 2008 annual budget for the Salem Corporation. The cost behavior pattern of the maintenance costs must be determined for this budget. The accounting staff has suggested that linear regression be employed to derive a cost estimation equation in the form of TC = F +VX for the total maintenance costs. Information regarding the maintenance hours and costs for 2007 and the partial results of the regression are as follows:     t-table for Single-Tailed Values of t    -Based upon the information from the regression analysis, the total maintenance costs budgeted for 420 hours of activity would be (rounded to the nearest whole dollar) : A)  $3,746 B)  $3,780 C)  $3,797 D)  $3,461 -Based upon the information from the regression analysis, the total maintenance costs budgeted for 420 hours of activity would be (rounded to the nearest whole dollar) :


A) $3,746
B) $3,780
C) $3,797
D) $3,461

Correct Answer

verifed

verified

A

A step or semifixed cost increases in a linear pattern as activity levels decrease.

Correct Answer

verifed

verified

False

The fixed cost per unit increases as the activity level increases within the relevant range.

Correct Answer

verifed

verified

Which of the following would not be a reason that a company would use cost estimation?


A) Determining opportunities for reducing costs without reducing value to customers
B) Determining how much to pay an employee
C) Determining a pricing policy to discourage particular customers and attract others
D) All of the above

Correct Answer

verifed

verified

If the learning curve for a production process is 80 percent, the time required to produce each unit is 80 percent of the time to produce the first unit.

Correct Answer

verifed

verified

Mundy Missiles Corp. is negotiating with the government for the production of cruise missiles. The government is considering purchasing either eight missiles for $2,500,000 or sixteen missiles for $5,000,000. Mundy requires a margin of 30 percent to cover administrative costs, research and development, and to make a profit. Mundy has started a chart for this product assuming the production costs are subject to an 80 percent cumulative learning curve. Mundy Missiles Corp. is negotiating with the government for the production of cruise missiles. The government is considering purchasing either eight missiles for $2,500,000 or sixteen missiles for $5,000,000. Mundy requires a margin of 30 percent to cover administrative costs, research and development, and to make a profit. Mundy has started a chart for this product assuming the production costs are subject to an 80 percent cumulative learning curve.    83. 1) Complete the chart (items a - f) by filling in the cost amounts for volumes 4, 8, and 16 units. 2) Should Mundy sell eight units? Sixteen units? 83. 1) Complete the chart (items a - f) by filling in the cost amounts for volumes 4, 8, and 16 units. 2) Should Mundy sell eight units? Sixteen units?

Correct Answer

verifed

verified

1)
(a) $320,000 ($400,000 x 80%)
(b) $1...

View Answer

In the formula, "TC = F + VX", X is considered to be the cost driver.

Correct Answer

verifed

verified

A regression analysis of total labor costs (y) based upon the number of visitors (x) for the Wacky World Theme Park, yielded a coefficient of $2.75. The t statistic was t=6.141 and the R2=.921. Based upon those results, we can conclude


A) The cost driver rate is $2.75 and statistically significant
B) Visitors cause all labor costs
C) The relationship between the t-statistic and the R2 is weak
D) All of the above

Correct Answer

verifed

verified

A

McNair School principal Dr. Ruth Gacoki wants to know whether the school recruitment program is successful. She used a spreadsheet to estimate the relationship between the number of advertisements and the number of phone inquiries received. Monthly data for the past two years were entered into the computer. Data includes months when no advertising was done through months with 1000 advertisements. Unfortunately, only part of the regression results printed before the computer froze. All Dr. Gacolki saw was "Intercept = 1200" R2 = .94. From that information she can conclude, with limited certainty, that:


A) For each advertisement, the school will receive 1200 more phone inquiries
B) There will be at least 1200 phone inquiries regardless of the advertisements
C) If 1,000 advertisements are placed, there will be 2130 phone inquiries
D) If 10 advertisements are placed, there will be 12,000 phone inquiries

Correct Answer

verifed

verified

The following graphs represent cost behaviors that a company might The following graphs represent cost behaviors that a company might     have: Required: For each of the following items, identify the graph that best illustrates the cost behavior: _____1. Supervisors' salaries where one supervisor is required for every 800 workers. _____2. Cost of direct materials used to produce bicycles is $2.40. _____3. Cost of inventory purchased which cost $2.00 per unit for the first 1,000 units purchased; the  next 300 units  can be purchased at a per unit price of $1.90; any units purchased above 1,3500 cost $2.07 per unit. _____4. Straight-line depreciation. ______5. Salaries of sales people where they receive a $1,000 flat fee per month plus a 4% commission  of sales. ______6. Lease of factory equipment with a fixed minimum payment of $1,000 for up to 400 machine  hours used,  plus $3 per hour up to 400 additional hours used, then a flat fee of $2,200plus $1.50 per hour for above 800 hours. ______7. Cost for water where the fee is $50 for using up to 100 acre feet per month, and then a $2 per  acre foot  used thereafter. ______8. Wages of delivery drivers where each driver can make 30 deliveries in one eight hour shift. have: Required: For each of the following items, identify the graph that best illustrates the cost behavior: _____1. Supervisors' salaries where one supervisor is required for every 800 workers. _____2. Cost of direct materials used to produce bicycles is $2.40. _____3. Cost of inventory purchased which cost $2.00 per unit for the first 1,000 units purchased; the next 300 units can be purchased at a per unit price of $1.90; any units purchased above 1,3500 cost $2.07 per unit. _____4. Straight-line depreciation. ______5. Salaries of sales people where they receive a $1,000 flat fee per month plus a 4% commission of sales. ______6. Lease of factory equipment with a fixed minimum payment of $1,000 for up to 400 machine hours used, plus $3 per hour up to 400 additional hours used, then a flat fee of $2,200plus $1.50 per hour for above 800 hours. ______7. Cost for water where the fee is $50 for using up to 100 acre feet per month, and then a $2 per acre foot used thereafter. ______8. Wages of delivery drivers where each driver can make 30 deliveries in one eight hour shift.

Correct Answer

verifed

verified

(1.) f (2.) b (3.) i...

View Answer

Processing costs in the billing department of Alfaro Company are a mixture of variable and fixed components. Records indicate that average unit processing costs are $0.50 per account processed at an activity level of 32,000 accounts. When only 22,000 accounts are processed, the total cost of processing is $12,500. Given these data, at a budgeted level of 25,000 accounts:


A) Processing costs are expected to total $8,750
B) Fixed processing costs are expected to be $10,400
C) The variable processing costs are expected to be $0.35 per account processed
D) Processing costs are expected to total $13,000

Correct Answer

verifed

verified

Which method of cost estimation does not use the company records as its primary source of cost-activity data?


A) Engineering estimates
B) Regression analysis
C) Account analysis
D) High-low method

Correct Answer

verifed

verified

Using the high-low method, which of the following could be used to calculate the intercept?


A) Total cost at highest cost driver level - (Variable cost per unit times the highest level)
B) Total cost at lowest cost driver level - (Variable cost per unit times the lowest level)
C) Either of the above
D) Neither of the above

Correct Answer

verifed

verified

What is cost estimation, and what is its purpose? What are the problems involved in cost estimation?

Correct Answer

verifed

verified

Cost estimation is the process of estima...

View Answer

Showing 1 - 20 of 90

Related Exams

Show Answer