A) discounted payback
B) net present value
C) internal rate of return
D) profitability index
Correct Answer
verified
Multiple Choice
A) Discounted payback = 4.25 years; accept the project
B) Discounted payback = 3.50 years; accept the project
C) Discounted payback > 5 years; reject the project
D) Discounted payback = 4.67 years; reject the project
Correct Answer
verified
Multiple Choice
A) The project's MIRR is 14.77% and the project should be accepted.
B) The project's MIRR is 9.29% and the project should be rejected.
C) The project's MIRR is 13.76% and the project should be accepted.
D) The project's MIRR is 15.31% and the project should be accepteD.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) is the average rate of return necessary to pay back the project's capital providers
B) will change with the cost of capital
C) is equal to the discounted cash flows divided by the number of cash flows if the cash flows are a perpetuity
D) All of these answers are correct.
Correct Answer
verified
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) cost of capital
B) managers' maximum number of years
C) zero or anything larger than zero
D) zero or anything less than zero
Correct Answer
verified
Multiple Choice
A) render the same investment decision.
B) use the same measurement units.
C) include all crucial information.
D) exclude some crucial information.
Correct Answer
verified
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) 1
B) 2
C) 3
D) 4
Correct Answer
verified
Multiple Choice
A) MIRR = 11.59%; accept the project
B) MIRR = 9.21%; reject the project
C) MIRR = 7.19%; reject the project
D) MIRR = 10.58%; accept the project
Correct Answer
verified
Multiple Choice
A) 15.24%
B) 15.96%
C) 16.17%
D) 15.42%
Correct Answer
verified
Multiple Choice
A) We have recovered all our costs
B) We are creating wealth for shareholders
C) The project's expected return exceeds the cost of capital
D) All of these
Correct Answer
verified
Multiple Choice
A) Project B because it has the higher NPV.
B) Project B because it has the higher IRR.
C) Project A because it has the higher NPV.
D) Project A because it has the higher IRR.
Correct Answer
verified
Multiple Choice
A) The project's PI is 8.48% and the project should be accepted.
B) The project's PI is 8.48% and the project should be rejected.
C) The project's PI is 16.48% and the project should be accepted.
D) The project's PI is 21.48% and the project should be accepteD.Step 1: Find NPV using financial calculator: NPV = 214.78; Step 2: 214.78/1000 = 21.48% and since PI>0 accept.
Correct Answer
verified
Multiple Choice
A) NPV
B) IRR
C) Payback
D) MIRR
Correct Answer
verified
Multiple Choice
A) 12.00%, reject
B) 31.21%, accept
C) 54.22%, accept
D) 80.67%, accept
Correct Answer
verified
Multiple Choice
A) It works equally well for independent and mutually exclusive projects
B) Managers have a preference for using a statistic that is in percent instead of dollars
C) It uses a conservative reinvestment rate assumption
D) These are all strengths of the NPV statistic
Correct Answer
verified
Multiple Choice
A) MIRR = 13.59%; accept the project
B) MIRR = 7.96%; reject the project
C) MIRR = 7.19%; reject the project
D) MIRR = 12.58%; accept the project
Correct Answer
verified
Showing 1 - 20 of 121
Related Exams