A) IRR = 16.92%; accept the project
B) IRR = 7.123%; reject the project
C) IRR = 18.32%; accept the project
D) IRR = 7.59%; reject the project
Correct Answer
verified
Multiple Choice
A) time or resource constraints.
B) a labor union.
C) the election of a new board of directors.
D) a major investment.
Correct Answer
verified
Multiple Choice
A) discounted payback
B) net present value
C) modified internal rate of return
D) profitability index
Correct Answer
verified
Multiple Choice
A) $9,704.31, reject
B) $84,140.71, accept
C) $134,704.31, accept
D) $150,868.83, accept
Correct Answer
verified
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) 33.26%
B) 34.98%
C) 35.93%
D) 36.72%
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Payback = 4.90 years; reject
B) Payback = 4.40 years; reject
C) Payback = 5.80 years; reject
D) Payback > 6.00 years; reject
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Discounted payback solves all the shortcomings of payback.
B) The reinvestment rate of NPV and MIRR is the same.
C) The MIRR and IRR have the same reinvestment rate.
D) All of these are correct statements.
Correct Answer
verified
Multiple Choice
A) 3.45 years, reject
B) 3.86 years, reject
C) 3.45 years, accept
D) 3.86 years, accept
Correct Answer
verified
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) 3.4375 years, accept
B) 3.78 years, reject
C) 4.4375 years, reject
D) 4.78 years, accept
Correct Answer
verified
Multiple Choice
A) 10%, reject
B) 14.22%, accept
C) 13.26%, accept
D) 18.96%, accept
Correct Answer
verified
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) Project B because it has the higher NPV.
B) Project B because it has the higher IRR.
C) Project A because it has the higher NPV.
D) Project A because it has the higher IRR.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) accept both A and B
B) accept neither A nor B
C) accept A, reject B
D) reject A, accept B
Correct Answer
verified
Multiple Choice
A) -.0977%, reject
B) -9.77%, reject
C) -24.41%, reject
D) 24.41%, accept
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Showing 41 - 60 of 121
Related Exams