A) The project's internal rate of return (IRR) is less than the discount (hurdle) rate.
B) The project's accounting (book) rate of return exceeds the discount (hurdle) rate.
C) The project is not desirable in a present-value sense.
D) The project's net present value (NPV) is positive.
E) The project's IRR is equal to the weighted-average cost of capital.
Correct Answer
verified
Multiple Choice
A) Cash-flow bailout.
B) Cash-flow break-even.
C) Net present value (NPV) .
D) Discounted payback.
E) Accounting (book) rate of return (ARR) , based on average investment over the life of each project.
Correct Answer
verified
Multiple Choice
A) 12%.
B) 20%.
C) 32%.
D) 36%.
E) 40%.
Correct Answer
verified
Multiple Choice
A) During the initiation stage of the project (i.e., at time period 0) .
B) During the operation stage of the project (i.e., after time period 0) .
C) Either during the initiation stage or the operation stage.
D) During neither the initiation stage nor the operation stage.
E) Evenly during all three stages: initiation, operation, and final disposal.
Correct Answer
verified
Multiple Choice
A) Disposition (i.e., sale) of an existing asset at an amount different from the asset's net book value (NBV) .
B) Required increase in net working capital associated with an investment project.
C) Sale of an investment asset at the end of the asset's useful life.
D) Effect of depreciation expense associated with an investment project.
E) Annual net benefits (e.g., reduction in operating expenses) associated with a proposed investment.
Correct Answer
verified
Multiple Choice
A) Cash flow from operations.
B) Salvage value of an existing asset that would be sold.
C) Employee severance compensation.
D) Reduction of net working capital at the termination (expiration) of the proposed project.
E) Gain or loss on the disposal of the investment at the end of its useful life.
Correct Answer
verified
Essay
Correct Answer
verified
Multiple Choice
A) Monte Carlo simulation (MCS) .
B) The analytic hierarchy process (AHP) .
C) Correlation analysis.
D) Multiple regression analysis.
E) Linear programming.
Correct Answer
verified
Multiple Choice
A) $24,000.
B) $36,000.
C) $48,000.
D) $60,000.
E) $120,000.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) 12%.
B) 14%.
C) 17%.
D) 24%.
E) 34%.
Correct Answer
verified
Multiple Choice
A) Expansion option.
B) Exercise option.
C) Abandonment option.
D) Investment-timing option (e.g., delay)
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) A single-criterion decision technique that can combine qualitative and quantitative factors in the overall evaluation of decision alternatives.
B) A multi-criteria decision technique that can combine qualitative and quantitative factors in the overall evaluation of decision alternatives.
C) A technique that does not use qualitative factors in the evaluation of decision alternatives.
D) A technique that focuses on qualitative factors in the evaluation of decision alternatives.
E) Not useful in choosing between two mutually exclusive capital budgeting projects.
Correct Answer
verified
Multiple Choice
A) Taxable cash receipts times (1 − t) .
B) Taxable cash receipts times t.
C) Taxable cash receipts times (1 + t) .
D) Taxable cash receipts divided by (1 − t) .
E) Taxable cash receipts divided by t.
Correct Answer
verified
Multiple Choice
A) The lack of good data.
B) Uncertainty about future events.
C) The large dollar amounts involved.
D) Income tax effects.
E) Lack of available forecasting tools.
Correct Answer
verified
Multiple Choice
A) Estimate a project's internal rate of return (IRR) .
B) Determine the optimal contribution margin given a set of resource constraints.
C) Determine the amount that a variable in a decision model (e.g., annual after-tax cash inflows) can change without changing the indicated decision (e.g., acceptance of a project) .
D) Simulate probabilistic customer reactions to a new product.
E) Capture income tax consequences.
Correct Answer
verified
Multiple Choice
A) The theoretical development of appropriate decision models.
B) Linkage of capital investment projects to the organization's Balanced Scorecard (BSC) .
C) Conducting post-audits of capital investment decisions.
D) Generation of relevant (i.e., cash flow) data for investment-analysis purposes.
E) Performing sensitivity or "what-if" analysis of proposed capital investments.
Correct Answer
verified
Multiple Choice
A) PV of after-tax cash outflows exceeds the PV of after-tax cash inflows.
B) Payback period is less than one-half the life of the project.
C) Internal rate of return (IRR) is equal to the discount percentage used in the NPV calculation.
D) PV index would be less than 100%.
E) Internal rate of return (IRR) for this project is greater than the discount rate used in the NPV computation.
Correct Answer
verified
Multiple Choice
A) What-if analysis.
B) Monte Carlo simulation.
C) Scenario analysis.
D) Linear programming.
E) Real options analysis.
Correct Answer
verified
Showing 81 - 100 of 167
Related Exams