Correct Answer
verified
Multiple Choice
A) Labor,material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.
Correct Answer
verified
Multiple Choice
A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Correct Answer
verified
Short Answer
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.
Correct Answer
verified
Multiple Choice
A) Direct costs are the lowest.
B) Indirect costs are the lowest.
C) Direct costs equal indirect costs.
D) Total project costs are the lowest.
E) The project changes from time-constrained to resource-constrained.
Correct Answer
verified
True/False
Correct Answer
verified
Not Answered
Correct Answer
verified
Not Answered
Correct Answer
verified
Multiple Choice
A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Linear.
B) Curvilinear.
C) Variable.
D) Conversely related.
E) Exponentially related.
Correct Answer
verified
Multiple Choice
A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.
Correct Answer
verified
Multiple Choice
A) Assign additional staff and equipment
B) Establish a core team
C) Do it twice-first fast and then correctly
D) Reduce project scope
E) Compromise quality
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Identify the critical path
E) Find the activity with the highest crash cost
Correct Answer
verified
Multiple Choice
A) Run by the rise.
B) Rise by the run.
C) Crash cost by the normal cost.
D) Normal cost by the crash cost.
E) Indirect cost by direct cost.
Correct Answer
verified
Multiple Choice
A) Earliest start time.
B) Most steep slope.
C) Least steep slope.
D) Longest duration.
E) Largest crash time.
Correct Answer
verified
Showing 1 - 20 of 94
Related Exams