Filters
Question type

Study Flashcards

The first step in the risk management process is risk assessment.

Correct Answer

verifed

verified

A list of questions that address traditional areas of uncertainty on a project is termed a


A) Risk profile.
B) Questionnaire.
C) Research matrix.
D) Query.
E) Checklist.

Correct Answer

verifed

verified

A fixed price contract is an example of


A) Avoiding risk.
B) Transferring risk.
C) Accepting risk.
D) Ignoring risk.
E) Mitigating risk.

Correct Answer

verifed

verified

Which of the following is NOT involved in risk control?


A) Executing the risk response strategy
B) Initiating contingency plans
C) Establishing a change control system
D) Establishing contingency funds
E) Watching for new risks

Correct Answer

verifed

verified

A key distinction between a risk response and a contingency plan is


A) A risk response is established only for moderate risks while contingency plans are established for major risks.
B) A risk response is part of the actual implementation plan and action is taken before the risk can materialize,while a contingency plan goes into effect only after the risk has transpired.
C) A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project;all other risks are covered by contingency planning.
D) A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.

Correct Answer

verifed

verified

_____________ is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action,that is,how much warning you would have.


A) Detection difficulty
B) Impact scaling
C) Probability analysis
D) Awareness level
E) Warning assessment

Correct Answer

verifed

verified

When developing a response to a risk by scheduling outdoor work in the summer,investing in up-front safety training,or choosing high-quality materials,these are examples of retaining a risk.

Correct Answer

verifed

verified

Responses to all identifiable risks should be a top priority for the project manager.

Correct Answer

verifed

verified

Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.


A) Risk breakdown structures
B) Contingency breakdown structures
C) Scenario analysis
D) Organizational breakdown structure
E) Risk assessment

Correct Answer

verifed

verified

When considering risk response development,reducing the likelihood that an event will occur and/or reducing the impact that an adverse event would have on a project is known as _________ the risk.

Correct Answer

verifed

verified

mitigating
Explanation: Reducing risk is...

View Answer

Change management systems involve reporting,controlling,and recording changes to the project baseline.

Correct Answer

verifed

verified

The risk management tool that is divided into three color-coded zones representing major,moderate,and minor risks is the risk


A) Assessment form.
B) Responsibility matrix.
C) Scenario assessment.
D) Impact assessment.
E) Severity matrix.

Correct Answer

verifed

verified

The risk identification process should be limited to just the core project team.

Correct Answer

verifed

verified

The initial step in the risk management process is to


A) Determine the level of acceptable risk.
B) Assess the risk potential.
C) Identify the risks.
D) Set aside budget funds for managing the risks.
E) Appoint a risk manager.

Correct Answer

verifed

verified

Purchasing an accident insurance policy would be an example of responding to a risk by _____________ it.


A) Mitigating
B) Retaining
C) Ignoring
D) Transferring
E) Avoiding

Correct Answer

verifed

verified

When considering risk response development,assuming the risk because the chance of such an event is slim is known as _________ the risk.

Correct Answer

verifed

verified

retaining
Explanation: Some risks are so...

View Answer

One common mistake made early in the risk identification process is to


A) Not consider all possibilities
B) Encourage participants be over optimistic
C) Support participants being over pessimistic
D) Focus on consequences and not on the events that could produce consequences
E) Give too much attention to past events

Correct Answer

verifed

verified

When considering risk management,what is an opportunity? List and briefly describe 4 different responses to an opportunity.

Correct Answer

verifed

verified

The measurement of how easy it would be to detect that the event was going to occur in time to take mitigating action is known as __________.

Correct Answer

verifed

verified

detection difficulty
Explanation: Detect...

View Answer

A risk is an uncertain event that,if it occurs,can have a positive or negative effect on project objectives.

Correct Answer

verifed

verified

Showing 41 - 60 of 86

Related Exams

Show Answer