Correct Answer
verified
Multiple Choice
A) Risk profile.
B) Questionnaire.
C) Research matrix.
D) Query.
E) Checklist.
Correct Answer
verified
Multiple Choice
A) Avoiding risk.
B) Transferring risk.
C) Accepting risk.
D) Ignoring risk.
E) Mitigating risk.
Correct Answer
verified
Multiple Choice
A) Executing the risk response strategy
B) Initiating contingency plans
C) Establishing a change control system
D) Establishing contingency funds
E) Watching for new risks
Correct Answer
verified
Multiple Choice
A) A risk response is established only for moderate risks while contingency plans are established for major risks.
B) A risk response is part of the actual implementation plan and action is taken before the risk can materialize,while a contingency plan goes into effect only after the risk has transpired.
C) A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project;all other risks are covered by contingency planning.
D) A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E) A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.
Correct Answer
verified
Multiple Choice
A) Detection difficulty
B) Impact scaling
C) Probability analysis
D) Awareness level
E) Warning assessment
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Risk breakdown structures
B) Contingency breakdown structures
C) Scenario analysis
D) Organizational breakdown structure
E) Risk assessment
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) Assessment form.
B) Responsibility matrix.
C) Scenario assessment.
D) Impact assessment.
E) Severity matrix.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Determine the level of acceptable risk.
B) Assess the risk potential.
C) Identify the risks.
D) Set aside budget funds for managing the risks.
E) Appoint a risk manager.
Correct Answer
verified
Multiple Choice
A) Mitigating
B) Retaining
C) Ignoring
D) Transferring
E) Avoiding
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Not consider all possibilities
B) Encourage participants be over optimistic
C) Support participants being over pessimistic
D) Focus on consequences and not on the events that could produce consequences
E) Give too much attention to past events
Correct Answer
verified
Not Answered
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Showing 41 - 60 of 86
Related Exams