Filters
Question type

Study Flashcards

Which of the following is provided by both the project network and the work breakdown structure?


A) Dependencies
B) Sequencing
C) Interrelationships
D) Activity duration
E) Timing

Correct Answer

verifed

verified

Information to develop a project network is collected from the


A) Organization breakdown structure.
B) Work breakdown structure.
C) Budget.
D) Project proposal.
E) Responsibility matrix.

Correct Answer

verifed

verified

System documentation cannot end until three days after testing has started.This is an example of which kind of lag?


A) Start to Start
B) Start to Finish
C) Finish to Finish
D) Finish to Start
E) Any of these could be correct

Correct Answer

verifed

verified

A(n)________ activity has more than one successor activity.

Correct Answer

verifed

verified

burst
Explanation: Burst activ...

View Answer

Which of the following is true about hammock activities?


A) They are used to identify the use of fixed resources or costs over a segment of a project
B) They are a combination of Start to Start and Start to Finish lags
C) They are activities in which the costs are not subject to change
D) They are an alternative description for the critical path
E) They are highly sensitive

Correct Answer

verifed

verified

Which of the following correctly calculates the early finish for an activity?


A) LS + DUR
B) ES + DUR
C) LF + DUR
D) ES + SL
E) LF + SL

Correct Answer

verifed

verified

In the network computation process what is a forward pass and what three things does it determine?

Correct Answer

verifed

verified

Concurrent engineering,which has dramatically reduced the development time for new products,relies on what kind of lag?


A) Start to Start lags
B) Start to Finish lags
C) Finish to Finish lags
D) Finish to Start lags
E) Any of these could be correct

Correct Answer

verifed

verified

The ________ calculates the earliest times that activities can start or finish.

Correct Answer

verifed

verified

forward pass Explanation: The forward pass describes how soon the activity can start (early start-ES)and how soon the activity can finish (early finish-EF).

An activity that has more than one dependency arrow flowing into it is termed a(n)


A) Parallel activity.
B) Critical path.
C) Burst activity.
D) Merge activity.
E) Independent activity.

Correct Answer

verifed

verified

D

Activities that can take place at the same time if the manager wishes them to are called ________ activities.

Correct Answer

verifed

verified

parallel
Explanation: Parallel activitie...

View Answer

A network has only one critical path and the slack for noncritical activities is high.This network would appear to have a _______ level of sensitivity

Correct Answer

verifed

verified

low
Explanation: Network sensitivity is ...

View Answer

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.

Correct Answer

verifed

verified

backward pass
Explanation: The backward ...

View Answer

Gantt charts are popular because they represent an easy-to-understand,clear picture on a time-scaled horizon.

Correct Answer

verifed

verified

Different activities along the same path can have different total slack.

Correct Answer

verifed

verified

A sequence of connected,dependent activities is termed a(n)


A) Path of events.
B) Parallel path.
C) Activity chain.
D) Path.
E) Dependent chain.

Correct Answer

verifed

verified

The amount of time an activity can be delayed and yet not delay the project is termed


A) Total slack.
B) Free slack.
C) Critical float.
D) Float pad.
E) Slip pad.

Correct Answer

verifed

verified

In the network computation process what is a backward pass and what four things does it determine?

Correct Answer

verifed

verified

The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.

Correct Answer

verifed

verified

Which of the following can be used without coordinating with managers of succeeding activities?


A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad

Correct Answer

verifed

verified

B

Showing 1 - 20 of 94

Related Exams

Show Answer