A) A graph of a project's NPV as a function of possible IRRs.
B) A graph of a project's NPV over time.
C) A graph of a project's NPV as a function of possible capital costs.
D) None of the statements are correct.
Correct Answer
verified
Multiple Choice
A) 0.23 years, accept
B) 1.77 years, accept
C) 2 years, accept
D) 4.33 years, reject
Correct Answer
verified
Multiple Choice
A) 15.45 percent
B) 15.12 percent
C) 13.57 percent
D) 12.71 percent
Correct Answer
verified
Multiple Choice
A) NPV = $1,766.55; accept the project
B) NPV =-$892.19; reject the project
C) NPV = $1,288.94; accept the project
D) NPV = -$3,577.90; reject the project
Correct Answer
verified
Multiple Choice
A) (-$639.96)
B) $360.04
C) $392.44
D) $486.29
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) 2.49 years, accept
B) 2.98 years, accept
C) 3.49 years, reject
D) 4.98 years, reject
Correct Answer
verified
Multiple Choice
A) The project's MIRR is 14.77 percent and the project should be accepted.
B) The project's MIRR is 9.29 percent and the project should be rejected.
C) The project's MIRR is 13.76 percent and the project should be accepted.
D) The project's MIRR is 15.31 percent and the project should be accepted.
Correct Answer
verified
Multiple Choice
A) its benchmark is not determined by a relevant external constraint.
B) it incorporates the time value of money.
C) it uses a conservative reinvestment rate.
D) none of the options.
Correct Answer
verified
Multiple Choice
A) Project B because it has the higher NPV.
B) Project B because it has the higher IRR.
C) Project A because it has the higher NPV.
D) Project A because it has the higher IRR.
Correct Answer
verified
Multiple Choice
A) 3.67 years, accept
B) 4.67 years, accept
C) 3.67 years, reject
D) 4.67 years, reject
Correct Answer
verified
Multiple Choice
A) 1.23 years, Accept
B) 2.45 years, accept
C) 2.77 years, accept
D) 5.36 years, reject
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) Internal rate of return (IRR)
B) Modified internal rate of return (MIRR)
C) Profitability index (PI)
D) Net present value (NPV)
Correct Answer
verified
Multiple Choice
A) we have recovered all our costs.
B) we are creating wealth for shareholders.
C) the project's expected return exceeds the cost of capital.
D) all of the options.
Correct Answer
verified
Multiple Choice
A) NPV
B) IRR
C) MIRR
D) None are suitable
Correct Answer
verified
Multiple Choice
A) the MIRR assumes that the cash inflows can be reinvested at the cost of capital.
B) the MIRR assumes that the cash inflows can be reinvested at the IRR.
C) the MIRR uses weighted-average dollars.
D) the MIRR uses input from the NPV whereas the IRR does not.
Correct Answer
verified
Multiple Choice
A) 1
B) 2
C) 3
D) Unable to determine unless we have the cost of capital.
Correct Answer
verified
Multiple Choice
A) causes the project's NPV to equal zero.
B) is used to discount cash flows when computing the project's NPV.
C) is used to determine which one of two mutually exclusive projects should be accepted.
D) is used to compute the project's discounted payback period.
Correct Answer
verified
Multiple Choice
A) MIRR.
B) profitability index.
C) IRR.
D) NPV.
Correct Answer
verified
Showing 61 - 80 of 113
Related Exams