Filters
Question type

Study Flashcards

Briefly explain timing options.

Correct Answer

verifed

verified

Companies with positive-NPV projects need not undertake them right away. If there are uncertainties associated with the project, costly mistakes might be avoided by waiting to resolve them. These types of options to postpone investment are called timing options.

Why is sensitivity analysis less realistic than Monte Carlo simulation?

Correct Answer

verifed

verified

Sensitivity analysis only changes one va...

View Answer

Monte Carlo simulation should be used to get the distribution of NPV values for a project.

Correct Answer

verifed

verified

The Taj Mahal Tour Company proposes to invest $3 million in a new tour package project.Fixed costs are $1 million per year.The tour package costs the company $500 to produce and can be sold at $1,500 per package to tourists.This tour package will last for the next five years.If the cost of capital is 20 percent, what is the NPV break-even number of tourists per year? (Ignore taxes.Round to the nearest 1,000.)


A) 1,000
B) 2,000
C) 3,000
D) 4,000

Correct Answer

verifed

verified

The following are drawbacks of sensitivity analysis except


A) it can provide ambiguous results.
B) the underlying variables are likely interrelated.
C) it can help identify the project's most important variables.
D) All of these statements are drawbacks of sensitivity analysis.

Correct Answer

verifed

verified

Firms that operate at break-even on an accounting profit basis are really losing the opportunity cost of capital on their investments.

Correct Answer

verifed

verified

A project requires an initial investment of $150.Your research generates the following estimates of revenues and costs (there are no taxes) :  Pessimistic  Mast Likely  Optimistic  Revenues 305065 Costs 202015\begin{array} { | l | c | c | c | } \hline & \text { Pessimistic } & \text { Mast Likely } & \text { Optimistic } \\\hline \text { Revenues } & \mathbf { 3 0 } & \mathbf { 5 0 } & \mathbf { 6 5 } \\\hline \text { Costs } & 20 & 20 & 15 \\\hline\end{array} The cost of capital equals 10 percent.Assume that the cash flows occur in perpetuity.Conduct a sensitivity analysis of the project's NPV to variations in costs.(Answers appear in order: [Pessimistic, Most Likely, Optimistic].)


A) +50, -100, +400
B) -50, +300, +500
C) -100, +150, +350
D) +100, +150, +200

Correct Answer

verifed

verified

The accounting break-even point occurs when


A) the total revenue line cuts the fixed cost line.
B) the present value of inflows line cuts the present value of outflows line.
C) the total revenue line cuts the total cost line.
D) total revenue is large enough to recapture depreciation expense.

Correct Answer

verifed

verified

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0) .You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60 percent of revenues.(Assume all revenues and costs occur at year-end [i.e., t = 1, t = 2, and t = 3]) .The equipment depreciates using straight-line depreciation over three years.At the end of the project, the firm can sell the equipment for $10,000 and also recover the investment in net working capital.The corporate tax rate is 30 percent and the cost of capital is 15 percent.What is the NPV of the project if the revenues were higher by 10 percent and the costs were 65 percent of the revenues?


A) $8,443
B) $964
C) $5,566
D) $4,840

Correct Answer

verifed

verified

The NPV break-even point occurs when


A) the present value of inflows line cuts the present value of outflows line.
B) the total revenue line cuts the fixed cost line.
C) the total revenue line cuts the total cost line.
D) the present value of inflows cuts the total cost line.

Correct Answer

verifed

verified

You are given the following net future values for harvesting trees from a plot of forestland.(This is a one-time harvest.)  Year 012345 Net Future Value 100125150175195210\begin{array} { l c c c c c c } \text { Year } & 0 & 1 & 2 & 3 & 4 & 5 \\\text { Net Future Value } & 100 & 125 & 150 & 175 & 195 & 210\end{array} If the cost of capital is 15 percent, calculate the optimal year to harvest.


A) Year 1
B) Year 2
C) Year 3
D) Year 4

Correct Answer

verifed

verified

After completing a project analysis, an analyst should rely on which tool to make a final recommendation on the project?


A) Sensitivity analysis
B) Break-even analysis
C) Decision trees
D) NPV

Correct Answer

verifed

verified

Which of the following simulation outputs is likely to be most useful and easy to interpret? The output that shows the distribution(s) of the project's


A) sales.
B) internal rate of return.
C) cash flows.
D) profits.

Correct Answer

verifed

verified

Tangible assets usually have higher abandonment values than intangible ones.

Correct Answer

verifed

verified

Which of the following statements most appropriately describes scenario analysis?


A) It looks at the project by changing one variable at a time.
B) It provides the break-even level of sales for the project.
C) It looks at different but consistent combinations of variables.
D) Each of these statements describes scenario analysis correctly.

Correct Answer

verifed

verified

One can employ simulation models to


A) understand the project better.
B) better understand forecasted cash flows.
C) assess the project risk.
D) understand the project better, better understand forecasted cash flows, and assess the project risk.

Correct Answer

verifed

verified

A project requires an initial investment in equipment of $90,000 and then requires an initial investment in working capital of $10,000 (at t = 0) .You expect the project to produce sales revenue of $120,000 per year for three years.You estimate manufacturing costs at 60 percent of revenues.(Assume all revenues and costs occur at year-end [i.e., t = 1, t = 2, and t = 3]) .The equipment depreciates using straight-line depreciation over three years.At the end of the project, the firm can sell the equipment for $10,000 and also recover the investment in net working capital.The corporate tax rate is 30 percent and the cost of capital is 12 percent. Calculate the NPV of the project.


A) $14,418
B) $8,443
C) $-2,735
D) $12,873

Correct Answer

verifed

verified

A

How do managers supplement the NPV analysis of a project to gain a better understanding of a project?

Correct Answer

verifed

verified

Generally, managers supplement the NPV a...

View Answer

Briefly discuss the usefulness of Monte Carlo simulation in project analysis.

Correct Answer

verifed

verified

Monte Carlo simulation can provide an ex...

View Answer

Projects with higher fixed costs have lower break-even points.

Correct Answer

verifed

verified

False

Showing 1 - 20 of 75

Related Exams

Show Answer