Lean emphasizes all of the following except:


A) Setup time reductions
B) Cross training of workers
C) Lot size reduction
D) Increased utilization of machines

Correct Answer

verifed

verified

Preventive maintenance is another term for stabilizing the master schedule.

Correct Answer

verifed

verified

False

A kanban card is used to signal that:


A) The next work center is stopped
B) A materials handler has run out of parts
C) A machine has broken down
D) Parts are needed by the subsequent work center
E) A machine is ready for preventive maintenance

Correct Answer

verifed

verified

The ideal setup time for a lean system is:


A) 5 minutes
B) The time it takes the line to get ready
C) 0 minutes
D) 1 hour

Correct Answer

verifed

verified

A kanban system cannot be used in service industries.

Correct Answer

verifed

verified

If it takes 100 minutes to complete a circuit,demand at the next work center is 5 parts per minute,and a kanban container holds 20 parts,how many containers are required?


A) 25
B) 5
C) 40
D) 20

Correct Answer

verifed

verified

Takt time is the available time for production divided by demand.

Correct Answer

verifed

verified

With lean thinking,a firm's operations layout should evolve to a cellular manufacturing layout.

Correct Answer

verifed

verified

One of the main objectives of a lean system is:


A) Striving for 'good enough'
B) Reduction of takt time
C) Reduction of waste
D) Define value from the manufacturer's perspective

Correct Answer

verifed

verified

How is the 5 Whys technique used in a lean system?

Correct Answer

verifed

verified

The 5 Whys technique is used for systemi...

View Answer

Define the English terms in the 5S technique.How is this applied in practice?

Correct Answer

verifed

verified

The 5S technique consists of: sort,strai...

View Answer

One of the keys to reducing inventory is reducing lead-time.

Correct Answer

verifed

verified

Which of the following is NOT generally an element of a lean system?


A) Flexible workforce
B) Type II MRP system
C) Stable master schedule
D) Kanban pull system

Correct Answer

verifed

verified

Why is a uniform load desirable in a lean system?


A) To balance the workload on all work centers
B) To allow for production of safety stock
C) To signal the need for more parts
D) To increase the time for scheduled maintenance

Correct Answer

verifed

verified

External setup time refers to:


A) The time it takes workers to set up a machine during scheduled maintenance
B) The time to complete setup activities that do not require that the machine be stopped
C) The time it takes equipment vendors to set up the machine
D) None of the above

Correct Answer

verifed

verified

B

Kaizen events typically take between 1 to 2 months.

Correct Answer

verifed

verified

Given the following information pertaining to item AX143,determine the appropriate number of kanban cards that should be used to support production. Demand rate = 500 units/week Time for container to complete circuit = 2 weeks Safety stock = 30 percent Size of container = 5 units


A) <100 units
B) Between 100 and 500 units
C) >500 units
D) There is not enough information to answer the question

Correct Answer

verifed

verified

Which of the following is not an element of lean?


A) Small-lot sizes
B) Modularized master schedule
C) Multifunction workers
D) Kanban pull system
E) Perfect or nearly perfect quality

Correct Answer

verifed

verified

The Japanese term for waste is "gemba."

Correct Answer

verifed

verified

False

Lean thinking can be applied to:


A) Manufacturing
B) Services
C) Functions other than operations
D) All of the above

Correct Answer

verifed

verified