A) Because the WACC incorporates the tax savings from debt, we can compute the levered value of an investment, which is its value including the benefit of interest tax shields given the firm's leverage policy, by discounting its future free cash flow using the WACC.
B) The WACC incorporates the benefit of the interest tax shield by using the firm's before-tax cost of capital for debt.
C) When the market risk of the project is similar to the average market risk of the firm's investments, then its cost of capital is equivalent to the cost of capital for a portfolio of all of the firm's securities; that is, the project's cost of capital is equal to the firm's weighted average cost of capital (WACC) .
D) A project's cost of capital depends on its risk.
Correct Answer
verified
Multiple Choice
A) $25.25
B) $13.25
C) $9.00
D) $18.50
Correct Answer
verified
Multiple Choice
A) $3.00
B) $1.05
C) $50.25
D) $17.60
Correct Answer
verified
Multiple Choice
A) optimal
B) minimal
C) maximal
D) nominal
Correct Answer
verified
Multiple Choice
A) In the flow-to-equity valuation method, the cash flows to equity holders are then discounted using the weighted average cost of capital.
B) In the WACC and APV methods, we value a project based on its free cash flow, which is computed ignoring interest and debt payments.
C) In the flow-to-equity (FTE) valuation method, we explicitly calculate the free cash flow available to equity holders taking into account all payments to and from debt holders.
D) The first step in the FTE method is to determine the project's free cash flow to equity (FCFE) .
Correct Answer
verified
Multiple Choice
A) $24 million
B) $50 million
C) $20 million
D) $15 million
Correct Answer
verified
Multiple Choice
A) constant
B) average
C) variable
D) zero
Correct Answer
verified
Multiple Choice
A) the weighted average cost of capital (WACC) method, the net present value (NPV) method, and the flow-to-equity (FTE) method.
B) the weighted average cost of capital (WACC) method, the adjusted present value (APV) method, and the debt-to-equity (DTE) method.
C) the weighted average cost of capital (WACC) method, the adjusted present value (APV) method, and the flow-to-equity (FTE) method.
D) the weighted average cost of capital (WACC) method, the adjusted future value (AFV) method, and the flow-to-equity (FTE) method.
Correct Answer
verified
Multiple Choice
A) the unlevered project and the income tax shield
B) the unlevered project and the CCA tax shield
C) the levered project and the interest tax shield
D) the unlevered project and the interest tax shield
Correct Answer
verified
Multiple Choice
A) interest tax shield; before-tax
B) expense tax shield; before-tax
C) interest tax shield; after-tax
D) expense tax shield; after-tax
Correct Answer
verified
Multiple Choice
A) The APV approach explicitly values the market imperfections and therefore allows managers to measure their contribution to value.
B) We need to know the debt level to compute the APV, but with a constant debt-equity ratio we need to know the project's value to compute the debt level.
C) The WACC method is more complicated than the APV method because we must compute two separate valuations: the unlevered project and the interest tax shield.
D) Implementing the APV approach with a constant debt-equity ratio requires solving for the project's debt and value simultaneously.
Correct Answer
verified
Multiple Choice
A) 10.3%
B) 9.9%
C) 10.1%
D) 9.5%
Correct Answer
verified
Multiple Choice
A) 8.0%
B) 7.5%
C) 7.0%
D) 9.0%
Correct Answer
verified
Multiple Choice
A) 10.00%
B) 7.75%
C) 8.25%
D) 8.50%
Correct Answer
verified
Showing 81 - 94 of 94
Related Exams