A) 30.10 percent
B) 29.83 percent
C) 22.47 percent
D) 31.38 percent
Correct Answer
verified
Multiple Choice
A) Payback
B) Discounted payback
C) Net present value
D) Profitability index
Correct Answer
verified
Multiple Choice
A) 2.49 years, accept
B) 2.98 years, accept
C) 3.49 years, reject
D) 4.98 years, reject
Correct Answer
verified
Multiple Choice
A) it works equally well for independent and mutually exclusive projects.
B) managers have a preference for using a statistic that is in percent instead of dollars.
C) it uses a conservative reinvestment rate assumption.
D) these are all strengths of the NPV statistic.
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) 12.00 percent, reject
B) 31.21 percent, accept
C) 54.22 percent, accept
D) 80.67 percent, accept
Correct Answer
verified
Multiple Choice
A) The project has only one negative cash flow.
B) The project's MIRR is less than 15 percent but greater than 10 percent.
C) The project's discounted payback is less than the project's payback.
D) The project's NPV > 0.
Correct Answer
verified
Multiple Choice
A) MIRR.
B) profitability index.
C) payback.
D) NPV.
Correct Answer
verified
Multiple Choice
A) 3.45 years, reject
B) 3.86 years, reject
C) 3.45 years, accept
D) 3.86 years, accept
Correct Answer
verified
Multiple Choice
A) MIRR.
B) profitability index.
C) IRR.
D) NPV.
Correct Answer
verified
Multiple Choice
A) NPV.
B) IRR.
C) P\payback.
D) MIRR.
Correct Answer
verified
Multiple Choice
A) we have recovered all our costs.
B) we are creating wealth for shareholders.
C) the project's expected return exceeds the cost of capital.
D) all of the options.
Correct Answer
verified
Multiple Choice
A) 33.26 percent
B) 34.98 percent
C) 35.93 percent
D) 36.72 percent
Correct Answer
verified
Multiple Choice
A) −$639.96
B) $360.04
C) $392.44
D) $486.29
Correct Answer
verified
Multiple Choice
A) either project if they both are more than managers' maximum payback period.
B) neither project if they both are less than managers' maximum payback period.
C) the project that pays back the soonest.
D) the project that pays back the soonest if it is equal to or less than managers' maximum payback period.
Correct Answer
verified
Multiple Choice
A) Accept both A and B
B) Accept neither A nor B
C) Accept A, reject B
D) Reject A, accept B
Correct Answer
verified
Multiple Choice
A) −0.0977 percent, reject
B) −9.77 percent, reject
C) −24.41 percent, reject
D) 24.41 percent, accept
Correct Answer
verified
Multiple Choice
A) MIRR = 11.59 percent; accept the project
B) MIRR = 9.21 percent; reject the project
C) MIRR = 7.19 percent; reject the project
D) MIRR = 10.58 percent; accept the project
Correct Answer
verified
Showing 101 - 119 of 119
Related Exams