Filters
Question type

Study Flashcards

The departmental overhead rate method uses a different overhead rate for each production department.

Correct Answer

verifed

verified

A company produces computer chips that go through two operations, operation A1 and operation B2, before they are complete.Expected costs and activities for the two departments are shown below.Departmental overhead rates are based on machine hours in department A1 and direct labor hours in department B2.Therefore, the overhead rates for department A1 and department B2 are $3.62 per machine hour and $5.73 per direct labor hour, respectively.  Department  Department  Al  B2  Machine hours 40,000MH30,000MH Direct labor hours 36,200DLH28,650DLH Overhead costs $144,800$171,900\begin{array} { l c c } & \text { Department } & \text { Department } \\& \text { Al } & \text { B2 } \\\text { Machine hours } & 40,000 \mathrm { MH } & 30,000 \mathrm { MH } \\\text { Direct labor hours } & 36,200 \mathrm { DLH } & 28,650 \mathrm { DLH } \\\text { Overhead costs } & \$ 144,800 & \$ 171,900\end{array}

Correct Answer

verifed

verified

Product design costs are an example of a unit level activity.

Correct Answer

verifed

verified

Batch level costs vary with the number of units produced.

Correct Answer

verifed

verified

In competitive markets, price is established through the forces of _______________ and _______________.

Correct Answer

verifed

verified

supply; de...

View Answer

A company uses activity-based costing to determine the costs of its three products: A, B, and C.The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:  Budgeted Activity  Activity Cost  Pool  Budgeted  Cost  Product A  Product B  Product C  Activity 1 $425,0001,7006801,870 Activity 2 $144,9001,8901,5752,835 Activity 3 $85,0002,4001,0001,600\begin{array}{r}{\text { Budgeted Activity }} \quad \quad \quad \quad \quad \quad \\\begin{array}{|l|r|r|r|r|}\hline \begin{array}{l}\text { Activity Cost } \\\text { Pool }\end{array} & {\begin{array}{l}\text { Budgeted } \\\text { Cost }\end{array}} & \text { Product A } & \text { Product B } & \text { Product C } \\\hline \text { Activity 1 } & \$ 425,000 & 1,700 & 680 & 1,870 \\\hline \text { Activity 2 } & \$ 144,900 & 1,890 & 1,575 & 2,835 \\\hline \text { Activity 3 } & \$ 85,000 & 2,400 & 1,000 & 1,600 \\\hline\end{array}\end{array} Compute the company's activity rates under activity-based costing for each of the three activities.

Correct Answer

verifed

verified

Activity 1: $425,000/(1,700 + ...

View Answer

Which of the following would not be considered a product cost?


A) Direct labor costs.
B) Factory supervisor's salary.
C) Factory line worker's salary.
D) Cost accountant's salary.
E) Manufacturing overhead costs.

Correct Answer

verifed

verified

Greene Company uses a plantwide overhead rate with direct labor hours as the allocation base.Use the following information to solve for the amount of direct labor hours estimated per unit of product G2.  Dreect material cost per unit of G 2 $7 Total estimated manufacturing overhead $795,000Total cost per unit of G 2 $20 Total estimated direct labor hours 530,000DLH Direct labor cost per unit of G 2 $3.70\begin{array}{lr} \text { Dreect material cost per unit of G 2 } &\$ 7 \\ \text { Total estimated manufacturing overhead } &\$ 795,000 \\ \text {Total cost per unit of G 2 } &\$ 20 \\ \text { Total estimated direct labor hours } &530,000 \\&\mathrm{DLH} \\ \text { Direct labor cost per unit of G 2 } &\$ 3.70\end{array}


A) 1.5 DLH per unit of G2.
B) 6.2 DLH per unit of G2.
C) 9.3 DLH per unit of G2.
D) .66 DLH per unit of G2.
E) 14.09 DLH per unit of G2.

Correct Answer

verifed

verified

In activity-based costing, an activity can involve several related tasks.

Correct Answer

verifed

verified

Activity-based costing often shifts overhead costs from large volume, standardized products to low-volume, specialty products that consume disproportionate resources.

Correct Answer

verifed

verified

Which of the following is true?


A) Overhead costs are often affected by many issues and are frequently too complex to be explained by any one factor.
B) The departmental overhead rate is not usually based on measures closely related to production volume.
C) The departmental overhead rate is most accurate in assigning overhead costs that are not driven by production volume.
D) Allocated overhead costs will be the same no matter which allocation method is used.
E) When cost analysts are able to logically trace cost objects to costs, costing accuracy is improved.

Correct Answer

verifed

verified

Identify and explain the four control levels associated with activity-based costing.

Correct Answer

verifed

verified

The four control levels associated with ...

View Answer

Which of the following statements is true with regard to the plantwide overhead rate method?


A) The rate is determined using volume-related measures.
B) It is logical to use this method when overhead costs are not closely tied to volume-related measures.
C) This method uses multiple overhead rates.
D) The rate is determined using measures that are not closely related to volume.
E) The method provides the most accurate means of allocating overhead costs.

Correct Answer

verifed

verified

Which types of overhead allocation methods result in the use of more than one overhead rate during the same time period?


A) Plantwide overhead rate method and departmental overhead rate method.
B) Cost pool overhead rate method and plantwide overhead rate method.
C) Departmental overhead rate method and activity-based costing.
D) Activity-based costing and plantwide overhead rate method.
E) Departmental overhead rate method and cost pool overhead rate method.

Correct Answer

verifed

verified

A company uses activity-based costing to determine the costs of its three products: A, B, and C.The activity rates and activity levels for each of the company's three activity cost pools are shown below.  Budgeted Activity  Activity Cost  Pool  Activity Rate  Product A  Product B  Product C  Activity 1 $197001,150650 Activity 2 $272,4002,1001,500 Activity 3 $626001,3501,050\begin{array}{r}{\text { Budgeted Activity }} \quad \quad \quad \quad \quad \quad \\\begin{array}{|l|r|r|r|r|}\hline \begin{array}{l}\text { Activity Cost } \\\text { Pool }\end{array} & \text { Activity Rate } & \text { Product A } & \text { Product B } & \text { Product C } \\\hline \text { Activity 1 } & \$ 19 & 700 & 1,150 & 650 \\\hline \text { Activity 2 } & \$ 27 & 2,400 & 2,100 & 1,500 \\\hline \text { Activity 3 } & \$ 62 & 600 & 1,350 & 1,050\\\hline\end{array}\end{array} Compute the company's budgeted cost for each of the three activities under activity-based costing.

Correct Answer

verifed

verified

None...

View Answer

Match each of the following terms a through j with the appropriate definitions 1 through 10.

Premises
An outgrowth of ABC that draws on the link between activities and cost incurrence for better management.
A collection of costs that are related to the same or similar activity.
Variable that causes a cost to go up or down.
The target of a cost assignment.
A measure of activity level.
A cost allocation method that focuses on activities performed.
An allocation rate used to assign a collection of related costs to a cost object.
Actions performed only on groups of units.
Actions which cause resources to be used.
Variable that causes an activity's cost to go up or down.
Responses
Cost pool
Cost driver
Activity-based management
Activity-based costing
Activity driver
Cost object
Pool rate
Activity
Activity cost driver
Batch level activities

Correct Answer

An outgrowth of ABC that draws on the link between activities and cost incurrence for better management.
A collection of costs that are related to the same or similar activity.
Variable that causes a cost to go up or down.
The target of a cost assignment.
A measure of activity level.
A cost allocation method that focuses on activities performed.
An allocation rate used to assign a collection of related costs to a cost object.
Actions performed only on groups of units.
Actions which cause resources to be used.
Variable that causes an activity's cost to go up or down.

A company allocates $7.50 overhead to each unit produced.The company uses a plantwide overhead rate with direct labor hours as the allocation base.Given the amounts below, how many direct labor hours does the company expect in department 2?  Estirnated:  Department 1  Departrnent 2 Maruffacturing overhead costs $74,358$49,572 Direct labor hours 6,610DLH?DLH Machinehours 700MH80MH\begin{array} { l c c } \text { Estirnated: } & \text { Department 1 } & \text { Departrnent } 2 \\\text { Maruffacturing overhead costs } & \$ 74,358 & \$ 49,572 \\\text { Direct labor hours } & 6,610 \mathrm { DLH } & ? \mathrm { DLH } \\\text { Machinehours } & 700 \mathrm { MH } & \mathbf { 8 0 \mathrm { MH } }\end{array}


A) 9,914 DLH
B) 6,612 DLH
C) 3,109 DLH
D) 7,454 DLH
E) 16,254 DLH

Correct Answer

verifed

verified

A company has two products: A1 and B2.It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:  Budgeted Activity  Activity Cost  Pool  Budgeted  Cost  Product A1  Product B2  Activity 1 $48,0001,2004,800 Activity 2 $3,0002,2404,760 Activity 3 $80,0007,200800\begin{array} { | l | l | r | r | } \hline & &{ \text { Budgeted Activity } } \\\hline \begin{array} { l } \text { Activity Cost } \\\text { Pool }\end{array} & \begin{array} { l } \text { Budgeted } \\\text { Cost }\end{array} & \text { Product A1 } & \text { Product B2 } \\\hline \text { Activity 1 } & \$ 48,000 & 1,200 & 4,800 \\\hline \text { Activity 2 } & \mathbf { \$ 3 , 0 0 0 } & \mathbf { 2 , 2 4 0 } & 4,760 \\\hline \text { Activity 3 } & \mathbf { \$ 8 0 , 0 0 0 } & 7,200 & \mathbf { 8 0 0 } \\\hline\end{array} Annual production and sales level of Product A1 is 8,480 units, and the annual production and sales level of Product B2 is 22,310 units.What is the approximate overhead cost per unit of Product A1 under activity-based costing?


A) $8.00
B) $9.00
C) $10.00
D) $12.00
E) $4.00

Correct Answer

verifed

verified

A company has two products: A1 and B2.It uses activity-based costing and has prepared the following analysis showing budgeted cost and activity for each of its three activity cost pools:  Budgeted Activity  Activity Cost  Pool  Budgeted  Cost  Product A1  Product B2  Activity 1 $48,0001,2004,800 Activity 2 $3,0002,2404,760 Activity 3 $80,0007,200800\begin{array} { | l | l | r | r | } \hline & &{ \text { Budgeted Activity } } \\\hline \begin{array} { l } \text { Activity Cost } \\\text { Pool }\end{array} & \begin{array} { l } \text { Budgeted } \\\text { Cost }\end{array} & \text { Product A1 } & \text { Product B2 } \\\hline \text { Activity 1 } & \$ 48,000 & 1,200 & 4,800 \\\hline \text { Activity 2 } & \mathbf { \$ 3 , 0 0 0 } & \mathbf { 2 , 2 4 0 } & 4,760 \\\hline \text { Activity 3 } & \mathbf { \$ 8 0 , 0 0 0 } & 7,200 & \mathbf { 8 0 0 } \\\hline\end{array} Annual production and sales level of Product A1 is 8,480 units, and the annual production and sales level of Product B2 is 22,310 units.What is the approximate overhead cost per unit of Product B2 under activity-based costing?


A) $8.00
B) $9.00
C) $10.00
D) $12.00
E) $4.00

Correct Answer

verifed

verified

A _______________________ overhead rate is a single overhead rate determined by using volume-related measures.

Correct Answer

verifed

verified

Showing 141 - 160 of 172

Related Exams

Show Answer