Filters
Question type

Study Flashcards

Lunicious Corporation currently produces baseball caps in an automated process.Expected production per month is 15,000 units,direct material costs are $3.50 per unit,and manufacturing overhead costs are $40,000 per month.Manufacturing overhead is entirely fixed costs.What is the flexible budget for 12,000 and 15,000 units,respectively?


A) $74,000; $92,500
B) $74,000; $84,500
C) $82,000; $92,500
D) $82,000; $84,500

Correct Answer

verifed

verified

Answer the following questions using the information below: Contrafic Corporation used the following data to evaluate its current operating system. The company sells items for $21 each and used a budgeted selling price of $21 per unit.  Actual  Budgeted  Units sold 180,000 units 185,000 units  Variable costs $1,080,000$1,295,000 Fixed costs $800,000$775,000\begin{array} { l r r } & \underline { \text { Actual } } & \text { Budgeted } \\\text { Units sold }& 180,000 \text { units } & 185,000 \text { units } \\\text { Variable costs } & \$ 1,080,000 & \$ 1,295,000 \\\text { Fixed costs }&\$ 800,000 & \$ 775,000\end{array} -What is the static-budget variance of variable costs?


A) $25,000 favorable
B) $25,000 unfavorable
C) $215,000 favorable
D) $215,000 unfavorable

Correct Answer

verifed

verified

A master budget is ________.


A) a budget which starts from a zero base
B) developed for a period for a planned output
C) developed at the end of a period
D) a type of flexible budget

Correct Answer

verifed

verified

B

Coffey Company maintains a very large direct materials inventory because of critical demands placed upon it for rush orders from large hospitals.Item A contains hard-to-get material Y.Currently,the standard cost of material Y is $4.00 per gram.During February,22,000 grams were purchased for $4.10 per gram,while only 20,000 grams were used in production.There was no beginning inventory of material Y. Required: a.Determine the direct materials price variance,assuming that all materials costs are the responsibility of the materials purchasing manager. b.Determine the direct materials price variance,assuming that all materials costs are the responsibility of the production manager. c.Discuss the issues involved in determining the price variance at the point of purchase versus the point of consumption.

Correct Answer

verifed

verified

a.
blured image b.
blured image c.Measuring the price variance...

View Answer

A variance is the difference between the actual cost for the current and expected (or budgeted)performance.

Correct Answer

verifed

verified

A favorable variance indicates that ________.


A) budgeted costs are less than actual costs
B) actual revenues exceed budgeted revenues
C) actual operating income is less than the budgeted amount
D) budgeted contribution margin is more than the actual amount

Correct Answer

verifed

verified

A favorable price variance for direct manufacturing labor might indicate that ________.


A) employees were paid more than planned
B) unexpected increase in direct labor rates
C) underskilled employees are being hired
D) congestion due to scheduling problems

Correct Answer

verifed

verified

Answer the following questions using the information below: These questions refer to flexible-budget variance formulas with the following descriptions for the variables: A = Actual; B = Budgeted; P = Price; Q = Quantity. -The best label for the formula (AP - BP) AQ is the ________.


A) efficiency variance
B) price variance
C) total flexible-budget variance
D) spending variance

Correct Answer

verifed

verified

The following data for the telephone company pertain to the production of 450 rolls of telephone wire during June.Selected items are omitted because the costing records were lost in a windstorm. The following data for the telephone company pertain to the production of 450 rolls of telephone wire during June.Selected items are omitted because the costing records were lost in a windstorm.   Required: Compute the missing elements in the report represented by the lettered items. Required: Compute the missing elements in the report represented by the lettered items.

Correct Answer

verifed

verified

None...

View Answer

Answer the following questions using the information below: Animent Industries, Inc. (AII) , developed standard costs for direct material and direct labor. In 2015, AII estimated the following standard costs for one of their major products, the 10-gallon plastic container.  Budgeted quantity  Budgeted price  Direct materials 0.10 pounds $60 per pound  Direct labor 0.05 hours $30 per hour \begin{array}{lll}&\text { Budgeted quantity }&\text { Budgeted price }\\\text { Direct materials } & 0.10 \text { pounds } & \$ 60 \text { per pound } \\\text { Direct labor } & 0.05 \text { hours } & \$ 30 \text { per hour }\end{array} During June, AII produced and sold 20,000 containers using 1,900 pounds of direct materials at an average cost per pound of $64 and 1,000 direct manufacturing labor-hours at an average wage of $30.50 per hour. -June's direct material flexible-budget variance is ________.


A) $7,200 unfavorable
B) $600 favorable
C) $1,600 unfavorable
D) $500 favorable

Correct Answer

verifed

verified

Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Paralith Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results.  Actual  Flexible  Static  Results  Budget  Budget  Sales volume (in units)  11,00010,000 Sales revenues $238,000$$230,000 Variable costs 150,000$180,000 Contribution margin 88,000$50,000 Fixed costs 36,000$35,000 Operating profit $52,000$$15,000\begin{array}{lccc} & \text { Actual } & \text { Flexible } & \text { Static } \\& \text { Results } & \text { Budget } & \text { Budget } \\\text { Sales volume (in units) } & 11,000 & & 10,000\\\\\text { Sales revenues } & \$ 238,000 & \$ & \$230,000 \\\text { Variable costs } & 150,000 & \$ & 180,000\\\\\text { Contribution margin }& 88,000& \$ &50,000\\\\\text { Fixed costs } & 36,000 & \$ & 35,000\\\text { Operating profit } & \$ 52,000& \$& \$ 15,000\end{array} -The flexible-budget variance for variable costs is ________.


A) $30,000 favorable
B) $31,000 unfavorable
C) $30,000 unfavorable
D) $48,000 favorable

Correct Answer

verifed

verified

Quindo Table Company manufactures tables for schools.The 2015 operating budget is based on sales of 44,000 units at $55 per table.Operating income is anticipated to be $132,000.Budgeted variable costs are $35 per unit,while fixed costs total $660,000. Actual income for 2015 was a surprising $477,000 on actual sales of 46,000 units at $57 each.Actual variable costs were $33 per unit and fixed costs totaled $627,000. Required: Prepare a variance analysis report with both flexible-budget and sales-volume variances.

Correct Answer

verifed

verified

Quindo Table Company Variance Analysis \(\begin{array}{|l|l|l|l|l|l|} \hline && \text { Flexible } & \text { Flexible } & \text { Volume } & \\ &\text { Actual Results } & \text { Variances } & \text { Budget } & \text { Variances } & \text { Sales-Static }\\ \hline \text { Urits sold } & 46,000 & & 46,000 & & 44,000 \\ \hline \text { Sales } & \$ 2,622,000 & \$ 92,000 \mathrm{~F} & \$ 2,530,000 & \$ 110,000 \mathrm{~F} & \$ 2,420,000 \\ \hline \begin{array}{l} \text { Variable } \\ \text { costs } \end{array} & 1,518,000 & 92,000 \mathrm{~F} & 1,610,000 & 70,000 \mathrm{U} & 1,540,000 \\ \hline \begin{array}{l} \text { Contributio } \\ \text { n margin } \end{array} & \$ 1,104,000 & \$ 184,000 \mathrm{~F} & \$ 920,000 & \$ 40,000 \mathrm{~F} & \$ 880,000 \\ \hline \text { Fixed costs } & 627,000 & 33,000 \mathrm{~F} & 660,000 & 0 & 660,000 \\ \hline \begin{array}{l} \text { Operating } \\ \text { income } \end{array} & \$ 477,000 & \$ 217,000 \mathrm{~F} & \$ 260,000 & \$ 40,000 \mathrm{~F} & \$ 220,000 \\ \hline \end{array}\) Total flexible-budget variance = $217,000 favorable. Total sales-volume variance = $40,000 favorable.

Answer the following questions using the information below: Genent Company manufactures tires. Some of the company's data was misplaced. Use the following information to replace the lost data:  Actual  Flexible Budget  Flexible  Sales-Volume  Static  Results  Variances  Budget  Variances  Budget  Units sold 495,000495,000453,750 Revenues $185,150$4,400 F( A) $6,160U(B)  Variable  costs (C) $880U$69,780$10,300 F$88,080 Fixed costs $36,430$3,770 F$40,2000$40,200 Operating  income $78,060(D) $70,770(E) $66,630\begin{array}{|l|r|r|r|r|r|}\hline &\text { Actual } & \text { Flexible Budget } & \text { Flexible } & \text { Sales-Volume } & \text { Static } \\&\text { Results } & \text { Variances } & \text { Budget } & \text { Variances } & \text { Budget } \\\hline\text { Units sold } & 495,000 & & 495,000 & & 453,750 \\\hline \text { Revenues } & \$ 185,150 & \$ 4,400 \mathrm{~F} & (\mathrm{~A}) & \$ 6,160 \mathrm{U} & (\mathrm{B}) \\\hline \text { Variable } & & & & & \\\text { costs } & (\mathrm{C}) & \$ 880 \mathrm{U} & \$ 69,780 & \$ 10,300 \mathrm{~F} & \$ 88,080 \\\hline \text { Fixed costs } & \$ 36,430 & \$ 3,770 \mathrm{~F} & \$ 40,200 & 0 & \$ 40,200 \\\hline \text { Operating } & & & & & \\\text { income } & \$ 78,060 & (\mathrm{D}) & \$ 70,770 & (\mathrm{E}) & \$ 66,630\\\hline\end{array} -What are the actual variable costs (C) ?


A) $72,800
B) $70,660
C) $62,640
D) $54,080

Correct Answer

verifed

verified

Answer the following questions using the information below: The actual information pertains to the month of September. As a part of the budgeting process, Twilith Fencing Company developed the following static budget for September. Twilith is in the process of preparing the flexible budget and understanding the results.  Actual  Results  Flexible  Budget  static  Budget  Sales volume (in units)  12,00015,000 Sales revenues $600,000$$750,000 Variable costs 307,200$360,000 Contribution margin 292,800$7390,000 Fixed costs 274,800$270,000 Operating profit $18,000$$120,000\begin{array}{lrrr}&\begin{array}{r}\text { Actual } \\\text { Results }\end{array} & \begin{array}{r}\text { Flexible } \\\text { Budget }\end{array} & \begin{array}{r}\text { static } \\\text { Budget }\end{array}\\\text { Sales volume (in units) } & 12,000 & & 15,000 \\\text { Sales revenues } & \$ 600,000 & \$ & \$ 750,000 \\\text { Variable costs } & 307,200 & \$ & 360,000\\\text { Contribution margin }&292,800&\$&7390,000\\\text { Fixed costs } & 274,800& \$ & 270,000 \\\text { Operating profit } & \$ 18,000 & \$ & \$ 120,000\end{array} -The flexible budget will report ________ for the fixed costs.


A) $343,500
B) $270,000
C) $274,800
D) $216,000

Correct Answer

verifed

verified

An unfavorable variance is conclusive evidence of poor performance.

Correct Answer

verifed

verified

If variance analysis is used for performance evaluation,managers are encouraged to meet targets using creativity and resourcefulness.

Correct Answer

verifed

verified

Which of the following is an example of nonfinancial performance measure?


A) percentage of products started and completed without requiring any rework
B) direct manufacturing labor efficiency variance
C) direct materials price variance
D) quantity discounts obtained on order of large quantity

Correct Answer

verifed

verified

Standard labor rate is $8 per hour.Standard labor allowed per unit is 0.6 hours.Actual cost per labor hour is $7.5 and actual labour hour per unit is 0.7 hours.What is the standard labor cost per output unit?


A) $4.5
B) $4.8
C) $5.6
D) $5.25

Correct Answer

verifed

verified

A purchasing manager's performance is best evaluated using the ________.


A) direct materials price variance
B) direct materials flexible-budget variance
C) direct manufacturing labor flexible-budget variance
D) affect the manager's action has on total costs for the entire company

Correct Answer

verifed

verified

D

If manufacturing machines are breaking down more than expected,this will contribute to a(n) ________.


A) favorable direct manufacturing labor price variance
B) unfavorable direct manufacturing labor price variance
C) favorable direct manufacturing labor efficiency variance
D) unfavorable direct manufacturing labor efficiency variance

Correct Answer

verifed

verified

Showing 1 - 20 of 180

Related Exams

Show Answer