Filters
Question type

Study Flashcards

Oroz Company had the following information available: Expected Costs and Selling Price Based on 5,000 units: Variable manufacturing costs per unit $32Fixed manufacturing costs per unit $20 Selling price per unit$70\begin{array} { l } \text {Variable manufacturing costs per unit }&\$32 \\ \text {Fixed manufacturing costs per unit }&\$20 \\ \text { Selling price per unit}&\$70 \\\end{array}  Expected production level5,000 unite \begin{array} { l } \text { Expected production level}& \text {5,000 unite }\\\end{array} In the flexible budget at 10,000 units,what is the total manufacturing cost?


A) $250,000
B) $420,000
C) $520,000
D) $700,000

Correct Answer

verifed

verified

Brad Company planned to produce 12,000 units.This level of production required 20 setups at a cost of $18,000 plus $500 per setup.Actual production was 10,000 units,requiring 15 setups.Actual setup cost was $26,000.What is the static budget variance for setup costs?


A) $2,000 Favorable
B) $2,000 Unfavorable
C) $2,500 Favorable
D) $2,500 Unfavorable

Correct Answer

verifed

verified

A company has the following information available about one of its products:  Standard price per pound of input ? Actual price per pound of input $27 Standard inputs per unit of output 3 pounds  Actual units of output 3,000 Direct Materials Price Variance $18,000 F Actual pounds of input used 9,000\begin{array}{ll}\text { Standard price per pound of input } & ? \\\text { Actual price per pound of input } & \$ 27 \\\text { Standard inputs per unit of output } & 3 \text { pounds } \\\text { Actual units of output } & 3,000 \\\text { Direct Materials Price Variance } & \$ 18,000 \mathrm{~F} \\\text { Actual pounds of input used } & 9,000\end{array} What is the standard price per pound of input?


A) $25
B) $27
C) $29
D) $33

Correct Answer

verifed

verified

The Tulip Company makes mugs for which the following standards have been developed:  Standard Inputs Expected  Standard Price  Expected  For Each Unit of Output  Per Unit of Input  Direct Materials 5 ounces $2 per ounce  Direct Labor 2.5 hours $8 per hour \begin{array}{lll}&\text { Standard Inputs Expected }&\text { Standard Price }\\\text { Expected }&\text { For Each Unit of Output }&\text { Per Unit of Input }\\\hline\text { Direct Materials } & 5 \text { ounces } & \$ 2 \text { per ounce } \\\text { Direct Labor } & 2.5 \text { hours } & \$ 8 \text { per hour }\end{array} Production of 400 mugs was expected in August,but 440 mugs were actually completed.Direct materials purchased and used were 2,100 ounces at an actual price of $2.20 per ounce.Direct labor cost for the month was $5,310,and the actual pay per hour was $9.00.What is the direct labor price variance for August?


A) $420 Favorable
B) $420 Unfavorable
C) $590 Favorable
D) $590 Unfavorable

Correct Answer

verifed

verified

As the terms are used in the budgeting process,it is possible for a company to be efficient at the same time it is ineffective.

Correct Answer

verifed

verified

In the relevant range,fixed overhead costs do not vary with cost driver activity.

Correct Answer

verifed

verified

The flexible budget variance for direct labor equals the labor price variance plus the labor quantity variance.

Correct Answer

verifed

verified

When preparing a flexible budget income statement,________ costs are constant at different levels of activity.


A) variable
B) step
C) contributed
D) fixed

Correct Answer

verifed

verified

The efficiency variance for fixed overhead costs ________.


A) is greater than the flexible budget variance for fixed overhead costs
B) is greater than the spending variance for fixed overhead costs
C) is greater than the flexible budget variance for variable overhead costs
D) does not exist

Correct Answer

verifed

verified

Dooley Company has the following information available for variable overhead costs.Direct labor hours are the cost driver for variable overhead costs.  Actual variable overhead costs $4,700 Standard variable overhead costs $1.20 per hou1  Actual direct labor hours 3,750 hours  Standard direct labor hours per unit 5 hours  Units produced 700\begin{array}{ll}\text { Actual variable overhead costs } & \$ 4,700 \\\text { Standard variable overhead costs } & \$ 1.20 \text { per hou1 } \\\text { Actual direct labor hours } & 3,750 \text { hours } \\\text { Standard direct labor hours per unit } & 5 \text { hours } \\\text { Units produced } & 700\end{array} What is the variable overhead efficiency variance?


A) $300 Favorable
B) $300 Unfavorable
C) $500 Favorable
D) $500 Unfavorable

Correct Answer

verifed

verified

Which of the following is used to develop flexible budgets?


A) fixed overhead variances
B) static budget variances
C) flexible budget variances
D) cost functions

Correct Answer

verifed

verified

The Matthew Company makes tables for which the following standards have been developed:  Standard Inputs Expected  Standard Price  Expected  For Each Unit of Output  Per Unit of Input  Direct Materials 7 ounces $5.20 per ounce  Direct Labor 3 hours $16 per hour \begin{array}{lll}&\text { Standard Inputs Expected }&\text { Standard Price }\\\text { Expected }&\text { For Each Unit of Output }&\text { Per Unit of Input }\\\hline\text { Direct Materials } & 7 \text { ounces } & \$5.20 \text { per ounce } \\\text { Direct Labor } & 3 \text { hours } & \$ 16 \text { per hour }\end{array} Production of 200 tables was expected in May,but 220 tables were actually completed.Direct materials purchased and used were 2,100 pounds at an actual price of $4.40 per pound.Direct labor cost for the month was $10,620,and the actual pay per hour was $18.00.What is the direct labor price variance for the month of May?


A) $1,180 Favorable
B) $1,180 Unfavorable
C) $1,200 Favorable
D) $1,200 Unfavorable

Correct Answer

verifed

verified

Potter Company has the following information:  Actual operating loss at 5,000 units $(11,000)  Budgeted operating income at 5,000 units $5,000 Budgeted operating income at 10,000 units $12,000 Planned level of operations 10,000 units  Actual level of operations 5,000 units \begin{array}{ll}\text { Actual operating loss at 5,000 units } & \$(11,000) \\\text { Budgeted operating income at 5,000 units } & \$ 5,000 \\\text { Budgeted operating income at 10,000 units } & \$ 12,000 \\\text { Planned level of operations } & 10,000 \text { units } \\\text { Actual level of operations } & 5,000 \text { units }\end{array} Assume the cost driver of product costs is units of production.What is the flexible budget variance for operating income?


A) $5,000 Unfavorable
B) $11,000 Unfavorable
C) $16,000 Unfavorable
D) $16,000 Favorable

Correct Answer

verifed

verified

If the total sales-activity variance and the static-budget variance are equal,there is no flexible budget variance.

Correct Answer

verifed

verified

Conner Company has the following information:  Actual operating loss at 5,000 units $(11,000)  Budgeted operating income at 5,000 units $5,000 Budgeted operating income at 10,000 units $12,000 Planned level of operations 10,000 units  Actual level of operations 5,000 units \begin{array}{ll}\text { Actual operating loss at 5,000 units } & \$(11,000) \\\text { Budgeted operating income at 5,000 units } & \$ 5,000 \\\text { Budgeted operating income at 10,000 units } & \$ 12,000 \\\text { Planned level of operations } & 10,000 \text { units } \\\text { Actual level of operations } & 5,000 \text { units }\end{array} Assume units of output are the cost driver for product costs.What is the static budget variance for operating income?


A) $11,000 Unfavorable
B) $12,000 Unfavorable
C) $23,000 Unfavorable
D) $23,000 Favorable

Correct Answer

verifed

verified

Unfavorable variances ________ represent bad decisions made by managers.


A) always
B) sometimes
C) never
D) none of the above

Correct Answer

verifed

verified

At 60,000 machine hours,Norwall Company's static budget for variable overhead costs is $180,000.At 60,000 machine hours,the company's static budget for fixed overhead costs is $300,000.Machine hours are the cost driver of all overhead costs.The static budget is based on 60,000 machine hours.At 60,000 machine hours,the company produces 40,000 units.The following data is available: Actual units produced and sold 42,000Actual machine hours 64,000Actual variable overhead costs $185,600Actual fixed overhead costs $302,400\begin{array} { l } \text {Actual units produced and sold }&42,000 \\ \text {Actual machine hours }&64,000 \\ \text {Actual variable overhead costs }& \$185,600\\ \text {Actual fixed overhead costs }&\$302,400 \\\end{array} What is the variable overhead spending variance?


A) $6,400 Unfavorable
B) $6,400 Favorable
C) $1,000 Favorable
D) $1,000 Unfavorable

Correct Answer

verifed

verified

A company that has an activity-based costing system with multiple cost drivers will prepare a(n) ________ budget.


A) financial planning
B) short-range planning
C) activity-based flexible
D) strategic

Correct Answer

verifed

verified

For fixed overhead costs,the spending variance is ________ equal to the flexible-budget variance.


A) always
B) sometimes
C) never
D) indeterminate

Correct Answer

verifed

verified

Kilsdonk Company has the following information available: Budgeted cost of direct materials at 900,000 units $900,000Budgeted cost of direct materials at 820,000 units $820,000Actual cost of direct materials at 820,000 units $840,000Actual level of output(units)  820,000Planned level of output(units)  900,000\begin{array} { l } \text {Budgeted cost of direct materials at 900,000 units }&\$900,000 \\ \text {Budgeted cost of direct materials at 820,000 units }&\$820,000 \\ \text {Actual cost of direct materials at 820,000 units }&\$840,000 \\ \text {Actual level of output(units) }&820,000 \\ \text {Planned level of output(units) }& 900,000\\\end{array} The cost driver of product costs is units of output.What is the static budget variance for direct material costs?


A) $20,000 Unfavorable
B) $20,000 Favorable
C) $60,000 Favorable
D) $60,000 Unfavorable

Correct Answer

verifed

verified

Showing 81 - 100 of 143

Related Exams

Show Answer