Which one of the following statements about material requirements planning is TRUE?


A) MRP is intended mainly for MRO (maintenance,repair,and operating supplies) items where the demands are not too "lumpy."
B) The more volatile the manufacturing environment,the more likely it is that an MRP installation will be successful.
C) Survey results show that most companies adopting MRP have a purely line flow strategy.
D) The distinctive advantages of MRP are greater when there are many BOM levels,large lot sizes,and a manufacturing environment that is not too volatile.

Correct Answer

verifed

verified

MRP ________ is a process that converts the requirements of various final products into a material requirements plan that specifies the replenishment schedule of all the subassemblies,components,and raw materials needed by the final products.

Correct Answer

verifed

verified

________ are orders that have been placed,but not yet completed.

Correct Answer

verifed

verified

A material requirements plan for each component item is generated from the master production schedule and other sources using an MRP explosion.

Correct Answer

verifed

verified

Table 13.3 Consider the following MPS,BOM,and inventory data.You will need a blank MRP record to answer the question(s) . Master Production Schedule: the following table shows the MPS start quantities. Week Table 13.3 Consider the following MPS,BOM,and inventory data.You will need a blank MRP record to answer the question(s) . Master Production Schedule: the following table shows the MPS start quantities. Week    Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Item    -Use the information in Table 13.3.Which one of the following statements about item C is TRUE? A) It has a planned receipt of 80 units in week 3. B) Its second planned order release is for 200 units in week 3. C) It has a planned receipt of 180 units in week 6. D) Its first planned order release is for 130 units in week 1. Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Item Table 13.3 Consider the following MPS,BOM,and inventory data.You will need a blank MRP record to answer the question(s) . Master Production Schedule: the following table shows the MPS start quantities. Week    Bill of Material -End item A uses 1 each of component C and 1 each of subassembly D. -Subassembly D uses 2 each of component E and 2 each of component F. -End item B uses 1 each of component C and 2 each of component F. Selected Inventory Data Item    -Use the information in Table 13.3.Which one of the following statements about item C is TRUE? A) It has a planned receipt of 80 units in week 3. B) Its second planned order release is for 200 units in week 3. C) It has a planned receipt of 180 units in week 6. D) Its first planned order release is for 130 units in week 1. -Use the information in Table 13.3.Which one of the following statements about item C is TRUE?


A) It has a planned receipt of 80 units in week 3.
B) Its second planned order release is for 200 units in week 3.
C) It has a planned receipt of 180 units in week 6.
D) Its first planned order release is for 130 units in week 1.

Correct Answer

verifed

verified

Enterprise resource planning (ERP)systems are small,functional information systems areas that support many enterprise processes and data storage needs.

Correct Answer

verifed

verified

Faster response to market changes and reduced inventory levels are both benefits of MRP.

Correct Answer

verifed

verified

Use the following MRP record to answer the question. Use the following MRP record to answer the question.   What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1,2,3,4,5,and 6) ? A) 35,0,0,60,0,0 B) 35,0,60,0,0,0 C) 5,30,0,40,20,0 D) 35,0,0,40,20,0 What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1,2,3,4,5,and 6) ?


A) 35,0,0,60,0,0
B) 35,0,60,0,0,0
C) 5,30,0,40,20,0
D) 35,0,0,40,20,0

Correct Answer

verifed

verified

Which one of the following is a feature of MRP II,but not available in basic MRP systems?


A) financial reporting
B) action notices
C) dispatch lists
D) capacity reporting

Correct Answer

verifed

verified

Lumpy dependent demand can result from continuous independent demand.

Correct Answer

verifed

verified

Management wishes to use a POQ lot-sizing rule for an item that experiences an average demand of 30 units per week.If the desired average lot size is 120 units,what should P be?


A) 0 or 1 weeks
B) 2 or 3 weeks
C) 4 or 5 weeks
D) More than 5 weeks

Correct Answer

verifed

verified

A(n)________ is a record of all the required materials,equipment time,staff,and other resources needed to provide a service,the parent-component relationship,and the usage quantities.

Correct Answer

verifed

verified

The principles of MRP should not be applied to distribution systems.

Correct Answer

verifed

verified

Table 13.4 Consider the MPS,BOM and inventory data shown below.Master Production Schedule: the following table shows the MPS start quantities. Week Table 13.4 Consider the MPS,BOM and inventory data shown below.Master Production Schedule: the following table shows the MPS start quantities. Week    Bill of Material -Item A uses 1 each of component D,2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item    -Use the information in Table 13.4.When does the first planned order release for item C occur? A) Week 1 or 2 B) Week 3 C) Week 4 D) No planned order releases needed Bill of Material -Item A uses 1 each of component D,2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item Table 13.4 Consider the MPS,BOM and inventory data shown below.Master Production Schedule: the following table shows the MPS start quantities. Week    Bill of Material -Item A uses 1 each of component D,2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item    -Use the information in Table 13.4.When does the first planned order release for item C occur? A) Week 1 or 2 B) Week 3 C) Week 4 D) No planned order releases needed -Use the information in Table 13.4.When does the first planned order release for item C occur?


A) Week 1 or 2
B) Week 3
C) Week 4
D) No planned order releases needed

Correct Answer

verifed

verified

Planned lead time for items manufactured in-house includes


A) setup time.
B) process time.
C) materials handling and waiting times.
D) all the above

Correct Answer

verifed

verified

________ is an algorithm designed to schedule a group of orders appropriately across an entire shop.

Correct Answer

verifed

verified

Finite cap...

View Answer

________ systems are large,integrated information systems that support many enterprise processes and data storage needs.

Correct Answer

verifed

verified

Enterprise...

View Answer

Which of the following statements concerning MRP is TRUE?


A) Dependent demand items tend to experience relatively constant demand rates.
B) MRP systems use independent demands for each component item.
C) Capacity requirements planning (CRP) uses open orders (scheduled receipts) and planned order releases to estimate capacity requirements for critical workstations.
D) The most accurate way to forecast dependent demand is to examine past usage rates.

Correct Answer

verifed

verified

Table 13.6 Table 13.6   -Use the information from Table 13.6.If the lot-sizing rule were L4L instead of FOQ = 30 units,what would be the planned order release quantity week 1? A) 0 units B) 10 units C) 20 units D) 40 units -Use the information from Table 13.6.If the lot-sizing rule were L4L instead of FOQ = 30 units,what would be the planned order release quantity week 1?


A) 0 units
B) 10 units
C) 20 units
D) 40 units

Correct Answer

verifed

verified

MRP is generally practiced on items emanating from independent demand.

Correct Answer

verifed

verified

Showing 121 - 140 of 151