Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) PERT
B) CPM
C) Gantt Chart
D) either PERT or CPM
E) PERT,CPM,or a Gantt chart are fine.
Correct Answer
verified
Multiple Choice
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer
verified
Multiple Choice
A) has been established by the Project Management Institute.
B) has been formulated by the Federal government.
C) has been formulated by the World Trade Organization.
D) is inappropriate,since everyone should use the same guidance on ethical issues.
E) does not exist at this time.
Correct Answer
verified
Multiple Choice
A) is unnecessary.
B) is impossible.
C) is prohibitively expensive.
D) may require crashing multiple tasks simultaneously.
E) can be done,but all critical tasks must be reduced in duration.
Correct Answer
verified
Multiple Choice
A) the simple average of the optimistic,pessimistic,and most likely times.
B) the weighted average of a,m,and b,with m weighted 4 times as heavily as a and b.
C) the sum of the optimistic,pessimistic,and most likely times.
D) the sum of the optimistic,pessimistic,and most likely times,divided by six.
E) the sum of the activity variances,divided by six.
Correct Answer
verified
Multiple Choice
A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) The most likely time is equivalent to the expected activity time.
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) work break schedule
B) work breakdown status
C) work breakdown schedule
D) work breakdown structure
E) work break status
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Multiple Choice
A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 98.
B) 108.
C) 109.
D) 115.
E) 118.
Correct Answer
verified
Multiple Choice
A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12
Correct Answer
verified
Multiple Choice
A) 2.00
B) 2.33
C) 2.67
D) 4.67
E) 14.00
Correct Answer
verified
Showing 21 - 40 of 120