Filters
Question type

Study Flashcards

Describe the differences between a Gantt chart and a PERT/CPM network.

Correct Answer

verifed

verified

The differences between a Gant...

View Answer

Slack is the amount of time an activity can be delayed without delaying the entire project.

Correct Answer

verifed

verified

A project manager is interested in crashing a project with variable activity times.Which of the following tools should he/she employ?


A) PERT
B) CPM
C) Gantt Chart
D) either PERT or CPM
E) PERT,CPM,or a Gantt chart are fine.

Correct Answer

verifed

verified

Which of the following statements regarding critical paths is true?


A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.

Correct Answer

verifed

verified

A code of ethics especially for project managers:


A) has been established by the Project Management Institute.
B) has been formulated by the Federal government.
C) has been formulated by the World Trade Organization.
D) is inappropriate,since everyone should use the same guidance on ethical issues.
E) does not exist at this time.

Correct Answer

verifed

verified

A network has been crashed to the point where all activities are critical.Additional crashing:


A) is unnecessary.
B) is impossible.
C) is prohibitively expensive.
D) may require crashing multiple tasks simultaneously.
E) can be done,but all critical tasks must be reduced in duration.

Correct Answer

verifed

verified

The expected activity time in PERT analysis is calculated as:


A) the simple average of the optimistic,pessimistic,and most likely times.
B) the weighted average of a,m,and b,with m weighted 4 times as heavily as a and b.
C) the sum of the optimistic,pessimistic,and most likely times.
D) the sum of the optimistic,pessimistic,and most likely times,divided by six.
E) the sum of the activity variances,divided by six.

Correct Answer

verifed

verified

Which of the following statements regarding PERT analysis is true?


A) Each activity has two estimates of its duration.
B) Project variance is the sum of all activity variances.
C) Project standard deviation is the sum of all critical activity standard deviations.
D) Only critical activities contribute to the project variance.
E) The most likely time is equivalent to the expected activity time.

Correct Answer

verifed

verified

The shortest of all paths through the network is the critical path.

Correct Answer

verifed

verified

Given the project within the table below,calculate the following: a.The critical path b.The minimum project duration c.The amount of slack for each activity Given the project within the table below,calculate the following: a.The critical path b.The minimum project duration c.The amount of slack for each activity

Correct Answer

verifed

verified

blured image (A)The critical path is CDEFG (B)Minimu...

View Answer

WBS stands for which of the following project management tools?


A) work break schedule
B) work breakdown status
C) work breakdown schedule
D) work breakdown structure
E) work break status

Correct Answer

verifed

verified

PERT,but not CPM,has the ability to consider the precedence relationships in a project.

Correct Answer

verifed

verified

Project managers have their own code of ethics,established by the Project Management Institute.

Correct Answer

verifed

verified

The ________ is a project management technique using only one time factor per activity that enables managers to schedule,monitor,and control large and complex projects.

Correct Answer

verifed

verified

critical p...

View Answer

Activity R on a CPM network has predecessors M and N,and has successor S.R has duration 5.N's late finish is 18,while M's is 20.S's late start is 14.Which of the following is definitely true?


A) R is critical and has zero slack.
B) R has no slack but is not critical.
C) The set of times cannot all be possible.
D) N is a critical activity.
E) S is a critical activity.

Correct Answer

verifed

verified

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates.

Correct Answer

verifed

verified

The critical path can be determined by use of either the "forward pass" or the "backward pass."

Correct Answer

verifed

verified

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64.There is a .90 probability that the project will be completed before approximately day:


A) 98.
B) 108.
C) 109.
D) 115.
E) 118.

Correct Answer

verifed

verified

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.   A) A-D-E; 5 B) B-E; 6 C) B-D-E; 7 D) A-C-E; 10 E) B-C-E; 12


A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12

Correct Answer

verifed

verified

An activity on a PERT network has these time estimates: optimistic = 1,most likely = 2,and pessimistic = 5.What is its expected activity time?


A) 2.00
B) 2.33
C) 2.67
D) 4.67
E) 14.00

Correct Answer

verifed

verified

Showing 21 - 40 of 120

Related Exams

Show Answer