Filters
Question type

Study Flashcards

To perform sensitivity analysis involving an integer linear program,it is recommended to


A) use the dual prices very cautiously.
B) make multiple computer runs.
C) use the same approach as you would for a linear program.
D) use LP relaxation.

Correct Answer

verifed

verified

Grush Consulting has five projects to consider.Each will require time in the next two quarters according to the table below. ​  Project  Time in first quarter  Time in second quarter  Revenue  A 5812000 B 31210000 C 7515000 D 235000 E 15120000\begin{array} { c c c c } \text { Project } & \text { Time in first quarter } & \text { Time in second quarter } & \text { Revenue } \\\hline \text { A } & 5 & 8 & 12000 \\\text { B } & 3 & 12 & 10000 \\\text { C } & 7 & 5 & 15000 \\\text { D } & 2 & 3 & 5000 \\\text { E } & 15 & 1 & 20000\end{array} Revenue from each project is also shown.Develop a model whose solution would maximize revenue,meet the time budget of 25 in the first quarter and 20 in the second quarter,and not do both projects C and D.

Correct Answer

verifed

verified

Let A = 1 if project A is selected,0 oth...

View Answer

The constraint x1 − x2 = 0 implies that if project 1 is selected,project 2 cannot be.

Correct Answer

verifed

verified

Let x1 and x2 be 0 - 1 variables whose values indicate whether projects 1 and 2 are not done or are done.Which answer below indicates that project 2 can be done only if project 1 is done?


A) x1 + x2 = 1
B) x1 + x2 = 2
C) x1 − x2 ≤ 0
D) x1 − x2 ≥ 0

Correct Answer

verifed

verified

Given the following all-integer linear program: ​ Max 3x1+2x23 x _ { 1 } + 2 x _ { 2 } s.t.  M.t. 3x1+2x23x1+x29x1+3x27x1+x21x1,x20 and integer \begin{array} { l l } \text { M.t. } & 3 x _ { 1 } + 2 x _ { 2 } \\ & 3 x _ { 1 } + x _ { 2 } \leq 9 \\ & x _ { 1 } + 3 x _ { 2 } \leq 7 \\ & - x _ { 1 } + x _ { 2 } \leq 1 \\ & x _ { 1 } , x _ { 2 } \geq 0 \text { and integer } \end{array} a.​Solve the problem as a linear program ignoring the integer constraints.Show that the optimal solution to the linear program gives fractional values for both x1 and x2. b.​What is the solution obtained by rounding fractions greater than of equal to 1/2 to the next larger number? Show that this solution is not a feasible solution. c.What is the solution obtained by rounding down all fractions? Is it feasible? d.​ ​ Enumerate all points in the linear programming feasible region in which both x1 and x2 are integers,and show that the feasible solution obtained in (c)is not optimal and that in fact the optimal integer is not obtained by any form of rounding.

Correct Answer

verifed

verified


a. From the graph on the next page, t...

View Answer

List and explain four types of constraints involving 0-1 integer variables only.

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

1. Binary Constraints: These constraints...

View Answer

Which of the following applications modeled in the textbook is an example of a fixed cost problem?​


A) ​supply chain design
B) ​bank location
C) ​capital budgeting
D) ​product design and market share optimization

Correct Answer

verifed

verified

​Assuming W1,W2 and W3 are 0 -1 integer variables,the constraint W1 + W2 + W3 < 1 is often called a


A) ​multiple-choice constraint.
B) ​mutually exclusive constraint.
C) ​k out of n alternatives constraint.
D) ​corequisite constraint.

Correct Answer

verifed

verified

If a problem has only less-than-or-equal-to constraints with positive coefficients for the variables,rounding down will always provide a feasible integer solution.

Correct Answer

verifed

verified

Simplon Manufacturing must decide on the processes to use to produce 1650 units.If machine 1 is used,its production will be between 300 and 1500 units.Machine 2 and/or machine 3 can be used only if machine 1's production is at least 1000 units.Machine 4 can be used with no restrictions. ​  Machine  Fixed  cost  Variable  cost  Minimum  Production  Maximum  Production 15002.00300150028000.50500120032003.001008004505.00 any  any \begin{array} { c c c c c } \text { Machine } & \begin{array} { c } \text { Fixed } \\\text { cost }\end{array} & \begin{array} { c } \text { Variable } \\\text { cost }\end{array} & \begin{array} { c } \text { Minimum } \\\text { Production }\end{array} & \begin{array} { c } \text { Maximum } \\\text { Production }\end{array} \\\hline 1 & 500 & 2.00 & 300 & 1500 \\2 & 800 & 0.50 & 500 & 1200 \\3 & 200 & 3.00 & 100 & 800 \\4 & 50 & 5.00 & \text { any } & \text { any }\end{array} (HINT: Use an additional 0 - 1 variable to indicate when machines 2 and 3 can be used. )

Correct Answer

verifed

verified


Let blured image the number of units ma...

View Answer

Rounding the solution of an LP Relaxation to the nearest integer values provides


A) a feasible but not necessarily optimal integer solution.
B) an integer solution that is optimal.
C) an integer solution that might be neither feasible nor optimal.
D) an infeasible solution.

Correct Answer

verifed

verified

The 0-1 variables in the fixed cost models correspond to


A) a process for which a fixed cost occurs.
B) the number of products produced.
C) the number of units produced.
D) the actual value of the fixed cost.

Correct Answer

verifed

verified

Why are 0 - 1 variables sometimes called logical variables?

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

0 - 1 variables are sometimes called log...

View Answer

Solve the following problem graphically. ​  Max X+2Y s.t. 6X+8Y487X+5Y35X,Y0Y is integer \begin{array} { l l } \text { Max } & X + 2 Y \\\text { s.t. } & 6 X + 8 Y \leq 48 \\& 7 X + 5 Y \geq 35 \\& X , Y \geq 0 \\& Y \text { is integer }\end{array} a.Graph the constraints for this problem.Indicate all feasible solutions. b.Find the optimal solution to the LP Relaxation.Round down to find a feasible integer solution.Is this solution optimal? c.Find the optimal solution.

Correct Answer

verifed

verified

a. The feasible region consists of the p...

View Answer

​The use of integer variables creates additional restrictions but provides additional flexibility.Explain.

Correct Answer

Answered by ExamLex AI

Answered by ExamLex AI

The use of integer variables creates add...

View Answer

If the LP relaxation of an integer program has a feasible solution,then the integer program has a feasible solution.

Correct Answer

verifed

verified

In a model involving fixed costs,the 0 - 1 variable guarantees that the capacity is not available unless the cost has been incurred.

Correct Answer

verifed

verified

Slack and surplus variables are not useful in integer linear programs.

Correct Answer

verifed

verified

Rounded solutions to linear programs must be evaluated for


A) feasibility and optimality.
B) sensitivity and duality.
C) relaxation and boundedness.
D) each of these choices are true.

Correct Answer

verifed

verified

The LP Relaxation contains the objective function and constraints of the IP problem,but drops all integer restrictions.

Correct Answer

verifed

verified

Showing 41 - 60 of 61

Related Exams

Show Answer