Filters
Question type

Study Flashcards

The costs of a completed job are transferred from the work-in-process inventory account to the finished goods inventory account.

Correct Answer

verifed

verified

Explain why actual costing systems are rarely used in practice.

Correct Answer

verifed

verified

Actual costing systems are rarely used i...

View Answer

The system which assign(s) costs by the job is termed:


A) The process costing system
B) The job-order costing system
C) The project costing system
D) Both a and c

Correct Answer

verifed

verified

When materials are purchased, the costs of the materials "flows" into the materials inventory account.

Correct Answer

verifed

verified

Stainless Steel Company has two production departments: A and B. Stainless Steel has following budgeted overhead costs and activity: Stainless Steel Company has two production departments: A and B. Stainless Steel has following budgeted overhead costs and activity:    Production data for job 20 and 21 are given below:       a. Compare the costs per unit of Job 20 if Stainless Steel uses 1. a plantwide rate based on direct labor hours; 2. a plantwide rate based on machine hours; 3. departmental rates with Department A based on direct labor hours and Department B using machine hours. (round to 2 decimal places) b. Why is there such a variation in the cost per unit? Which method provides the best cost assignment?  a. Compare the costs per unit of Job 20 if Stainless Steel uses Production data for job 20 and 21 are given below: Stainless Steel Company has two production departments: A and B. Stainless Steel has following budgeted overhead costs and activity:    Production data for job 20 and 21 are given below:       a. Compare the costs per unit of Job 20 if Stainless Steel uses 1. a plantwide rate based on direct labor hours; 2. a plantwide rate based on machine hours; 3. departmental rates with Department A based on direct labor hours and Department B using machine hours. (round to 2 decimal places) b. Why is there such a variation in the cost per unit? Which method provides the best cost assignment?  a. Compare the costs per unit of Job 20 if Stainless Steel uses Stainless Steel Company has two production departments: A and B. Stainless Steel has following budgeted overhead costs and activity:    Production data for job 20 and 21 are given below:       a. Compare the costs per unit of Job 20 if Stainless Steel uses 1. a plantwide rate based on direct labor hours; 2. a plantwide rate based on machine hours; 3. departmental rates with Department A based on direct labor hours and Department B using machine hours. (round to 2 decimal places) b. Why is there such a variation in the cost per unit? Which method provides the best cost assignment?  a. Compare the costs per unit of Job 20 if Stainless Steel uses a. Compare the costs per unit of Job 20 if Stainless Steel uses 1. a plantwide rate based on direct labor hours; 2. a plantwide rate based on machine hours; 3. departmental rates with Department A based on direct labor hours and Department B using machine hours. (round to 2 decimal places) b. Why is there such a variation in the cost per unit? Which method provides the best cost assignment? a. Compare the costs per unit of Job 20 if Stainless Steel uses

Correct Answer

verifed

verified

a. Overhead rates if Stainless Steel use...

View Answer

Figure 5 - 8 Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. Figure 5 - 8 Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year.    The following information about the jobs was given for April.    By April 30, Jobs 102 and 103 were completed and sold. The remaining jobs were still in process. -Refer to Figure 5-8. The ending work in process would consist of the costs of what jobs? A)  Job 102 + Job 103 B)  Job 101 + Job 104 C)  Job 101 + Job 102 + Job 103 + Job 104 D)  Job 101 + Job 102 + Job 103 The following information about the jobs was given for April. Figure 5 - 8 Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year.    The following information about the jobs was given for April.    By April 30, Jobs 102 and 103 were completed and sold. The remaining jobs were still in process. -Refer to Figure 5-8. The ending work in process would consist of the costs of what jobs? A)  Job 102 + Job 103 B)  Job 101 + Job 104 C)  Job 101 + Job 102 + Job 103 + Job 104 D)  Job 101 + Job 102 + Job 103 By April 30, Jobs 102 and 103 were completed and sold. The remaining jobs were still in process. -Refer to Figure 5-8. The ending work in process would consist of the costs of what jobs?


A) Job 102 + Job 103
B) Job 101 + Job 104
C) Job 101 + Job 102 + Job 103 + Job 104
D) Job 101 + Job 102 + Job 103

Correct Answer

verifed

verified

The absolute maximum production activity of a manufacturing firm is called:


A) Expected activity level
B) Normal activity level
C) Theoretical activity level
D) Practical activity level

Correct Answer

verifed

verified

Unit costs are critical for


A) valuing inventory.
B) determining net income.
C) decisions to enter a new product line.
D) all of the above.

Correct Answer

verifed

verified

The form indicates the type and quantity of each material issued to the factory.

Correct Answer

verifed

verified

materials ...

View Answer

The predetermined overhead rate is usually calculated at the


A) end of each month.
B) beginning of each month.
C) beginning of the year.
D) end of the year.

Correct Answer

verifed

verified

C

Figure 5 - 2 The Cameron Corporation manufactures custom-made purses. The following data pertains to Job XY5: Direct materials placed into production $4,000 Direct labor hours worked 50 hours Direct labor rate per hour $ 15 Machine hours worked 100 hours Factory overhead is applied using a plant-wide rate based on direct labor hours. Factory overhead was budgeted at $80,000 for the year and the direct labor hours were estimated to be 20,000. Job XY5 consists of 50 units. -Refer to Figure 5-2. What is overhead cost assigned to Job XY5?


A) $200
B) $400
C) $750
D) $1,500

Correct Answer

verifed

verified

In a job-order costing system, actual overhead costs never enter the work-in-process inventory accounts

Correct Answer

verifed

verified

Which cost accounting process would be most appropriate for accumulating costs of identical, standardized units?


A) job-order costing
B) process costing
C) normal costing
D) standard costing

Correct Answer

verifed

verified

When a job is shipped to a customer, the finished job cost becomes the cost of the sold.

Correct Answer

verifed

verified

Abnormal spoilage is charged to the job that caused it.

Correct Answer

verifed

verified

An actual overhead rate can be calculated


A) at the beginning of the year.
B) at the end of each month.
C) at the beginning of each month.
D) either at the beginning of the year or at the beginning of the month.

Correct Answer

verifed

verified

Perishability refers to the


A) nonphysical nature of services as opposed to products.
B) fact that production and consumption are inseparable for services.
C) greater chances for variation in the performance of services than in the production of products.
D) fact that services cannot be inventoried but must be consumed when performed.

Correct Answer

verifed

verified

Figure 5-5 Tonneau Corporation had the following information available for October 2016: Work in Process, October 1 $20,000 Materials placed into production, October 27,500 Direct labor, October 37,500 Factory overhead rate is 150 percent of direct labor costs. Job cost sheets had the following balances: Figure 5-5 Tonneau Corporation had the following information available for October 2016: Work in Process, October 1 $20,000 Materials placed into production, October 27,500 Direct labor, October 37,500 Factory overhead rate is 150 percent of direct labor costs. Job cost sheets had the following balances:    Jobs Z3 and Z4 were not completed at the end of December. -Refer to Figure 5-5. What is the cost of goods finished during October for Tonneau Corporation? A)  $85,000 B)  $87,500 C)  $56,250 D)  $53,750 Jobs Z3 and Z4 were not completed at the end of December. -Refer to Figure 5-5. What is the cost of goods finished during October for Tonneau Corporation?


A) $85,000
B) $87,500
C) $56,250
D) $53,750

Correct Answer

verifed

verified

B

The total applied overhead at a given point in time is given by the credit balance in the control account.

Correct Answer

verifed

verified

A debit to Materials Inventory indicates materials were


A) ordered.
B) requisitioned.
C) put into production.
D) purchased.

Correct Answer

verifed

verified

D

Showing 1 - 20 of 149

Related Exams

Show Answer