What is the labour efficiency variance for the month?

A) $7,230 F.
B) $7,230 U.
C) $9,150 F.
D) $9,150 U.

Labour Efficiency Variance

The difference between the actual labor hours spent on production and the expected (or standard) labor hours, multiplied by the standard labor rate.

Actual Total Labour Cost

The real amount spent on wages and benefits for employees involved in the production process during a specific period.

Standard Labour Rate

The pre-established rate per hour that a company expects to pay for direct labor.

  • Quantify the variances in materials and labor, including variances in price, quantity, rate, and efficiency.