Which of the following statements regarding critical paths is true?
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Critical Paths
The sequence of stages determining the minimum time needed to complete a project, highlighting the most important tasks that directly affect the completion time.
Slack
A measure of the flexibility in scheduling activities; it represents the amount of time that a task in a project can be delayed without causing a delay to subsequent tasks or the project completion date.
- Understand the importance and concept of critical paths in project networks.
Verified Answer
KL
Learning Objectives
- Understand the importance and concept of critical paths in project networks.
Related questions
The Shortest of All Paths Through the Network Is the ...
Every Network Has at Least One Critical Path
___ Allow Project Managers to Analyze, Plan, and Control Timetables ...
A Real Estate Developer Wants to Control Costs and Complete ...
Which of the Following Statements Regarding CPM Networks Is True ...